BLOCK 15. STM-64 MS-SPRING tests<br />
TCB008: Support <strong>for</strong> SDH STM-64 MS-SPRING (2-fibre)<br />
Purpose:<br />
Confirm support <strong>for</strong> 2 fibre STM-64 MS-SPRING (2-fibre)<br />
Equipment required:<br />
4 SDH test sets<br />
<strong>Test</strong> method:<br />
1. Start with a clean network – no circuits configured and no alarms<br />
2. Set up a VC4 circuit from LON#6 to NY#6<br />
<strong>Test</strong> <strong>Plan</strong> <strong>for</strong> <strong>Optical</strong> <strong>Grooming</strong> <strong>Switches</strong><br />
Expected result:<br />
• System is user-friendly enough that BTexact can set trail up in less than 10 minutes<br />
• Traffic is carried error free<br />
• Switch management system clearly shows route of circuit<br />
Any other comments:<br />
If supplier does not support 2-fibre MS-SPRING they may instead offer 4-fibre MS-SPRING<br />
<strong>for</strong> this test . Lack of support <strong>for</strong> 2-fibre MS-SPRING will be recorded.<br />
It is assumed that if the system supports OC-48 BLSR and STM-64 MS-SPRING then it will<br />
also support OC-192 BLSR<br />
TCB009: Confirm SPRING protection in event of card failure<br />
<strong>Test</strong> purpose:<br />
To confirm basic operation of an MS-SPRING and to confirm ring protection in event of card<br />
failure<br />
Equipment needed:<br />
4 SDH test sets<br />
<strong>Test</strong> method:<br />
1. Following successful completion of TCB008<br />
2. Set up second circuit on the ring – a VC4-16c from LA#8 to NY#7<br />
3. Pull out card LON#4<br />
Expected results:<br />
• VC4 circuit from LON#6 to NY#6 should see less than 50 ms loss of traffic<br />
• VC4-16c circuit from LA#8 to NY#7 should experience no loss of traffic<br />
• Within 10 seconds an alarm should be raised indicating card out<br />
• Switch management system should clearly show the circuit routings<br />
Any other comments:<br />
None<br />
TCB010: Confirm MS-SPRING reverts when card is replaced<br />
<strong>Test</strong> purpose:<br />
To confirm correct operation of MS-SPRING when card is replaced.<br />
Equipment needed:<br />
4 SDH testers<br />
51