Installation / System<br />
63 9810.0156 – Rev.04 –12/01/2007<br />
It is suggested that after installation filling and air<br />
ventilation processes are completed, installation pumps<br />
must circulate the water in the system about one hour. It is<br />
neccesary to release last air molecules and activate the<br />
system completely. During the test circulation, pump<br />
and/or pumps must be in use.<br />
Caution: Boiler must not be operated certainly<br />
without providing the water pressure completely and<br />
releasing the air in the installation.<br />
Boiler must be observed for a while after it is<br />
activated, boiler water level must be controlled and<br />
observed constantly by the suitable manometer which<br />
is mounted to a convenable and traceable place in the<br />
installation.<br />
In case of a different pump mounting onto boiler to<br />
provide hot water, circulation lines must be checked<br />
carefully. In case of 4 way valve usage, water heating<br />
installation should be done through another exchanger to<br />
prevent wrong circulation.<br />
Discharging of the Condense Water<br />
Caution! Condense water occured during heating process<br />
must be transferred via an convenable neutralizer<br />
installation(accessory). pH value is between 3 and 4 for<br />
gas fuels and between 2 and 3 for liquid fuels. Therefore<br />
suitable neutralizer must be used.<br />
Condense water line must be installed as slanting.<br />
The line going to channel connection must be seen clearly.<br />
Bottom drainage line must be under the chimney hood<br />
level.<br />
Neutralizer installation is not required for the liquid<br />
fuel which has low rate sulfur (In accordance with ATV note<br />
page A251). Generally , there is no need to neutralizer<br />
installation in the boiler having 200 kW nominal heating<br />
power.<br />
For the neutralization of the boiler outlet water,<br />
local waste water specifications and\or local specifications<br />
must be taken into consideration.<br />