Project Milestone Status Comment<br />
Agreement with Raukawa Settlement<br />
Trust<br />
Develop agreement<br />
Annual Plan <strong>2013</strong>/14<br />
(Sue M)<br />
Annual Report 2012/13<br />
(Sue M)<br />
Plan Changes <strong>28</strong>-33<br />
(Nick C.)<br />
Poihipi Road widening<br />
(Denis Lewis)<br />
Keys:<br />
Adopt draft plan for public consultation<br />
Hearings and deliberations<br />
Third quarter report<br />
Appeals<br />
Tender<br />
Construction<br />
<strong>Council</strong> has convened a joint committee, appointed four<br />
representatives and adopted terms of reference at the March<br />
<strong>Council</strong> meeting. The first meeting of the joint committee was<br />
held on 7 May and work is progressing^officer level.<br />
<strong>Council</strong> adopted the Draft Annual Plan on 18 March-<strong>2013</strong>.<br />
Consultation opened on 25 March and closed on 24 April <strong>2013</strong>.<br />
<strong>Council</strong> received 123 submissions.<br />
Hearings were held on 13 and 15 May <strong>2013</strong>. Deliberations will<br />
be conducted on the week of 20 May <strong>2013</strong>.<br />
The third quarter report covering January to March <strong>2013</strong> goes<br />
to <strong>Council</strong> in May <strong>2013</strong> as part of the CEO's report.<br />
Officers are working with the appellants and the Environment<br />
Court to structure the appeal process and initiate mediation.<br />
The contract has been let to Downer NZ Ltd.<br />
Earthworks have commenced and it is anticipated the project<br />
will be completed by the end of June.<br />
\0<br />
>^<br />
1°<br />
Completed/on track<br />
Slippage; milestone must be completed within the financial year. Explain reasons for the delay and how this is being addressed. Include expected new delivery date.<br />
Milestone is unlikely to be completed within the financial year OR the project is over budget.<br />
Project or all milestones are completed within budget for the year.