Poihipi Road Widening<br />

Scheme Poihipi Widening Month Number<br />

Contractor Downer N2 Ltd Month Ending 31 March <strong>2013</strong><br />

Budget $300,000 Contract Number TDC/1213/087<br />

Expenditure $75,000 Commencement Date 15 April <strong>2013</strong><br />

Commitments $235,000 Contract Completion Date 31 May <strong>2013</strong><br />

Forecast Cost $300,000 Anticipated Completion Date 31 May <strong>2013</strong><br />

.^<br />

.N>^<br />

~c-<br />

Overall Progress<br />

Construction commenced 15 April <strong>2013</strong>. 75% 75%<br />

Detailed Progress<br />

The project involves widening the road at three separate sites .Work commenced on 15 April and the widening at the first site<br />

is 100% completed. Earthworks and base course placement have been completed at the other two sites.<br />

Key Risks<br />

Adverse weather