Turangi Wastewater Treatment Plant Optimisation<br />

Scheme Turangi WWTP Optimisation Month Number<br />

Contractor n/a Month Ending 30 April <strong>2013</strong><br />

Budget $ 2,500,000 Contract Number<br />

Expenditure $ 60,498 Commencement Date<br />

Commitments $ 29,780 Contract Completion Date<br />

Forecast Cost $ 2,500,000 Anticipated Completion Date June 2014<br />

Overall Progress<br />

Investigation Phase<br />

Preliminary Design<br />

Detailed Design<br />

Construction<br />

90% (site trials to complete)<br />

40% (pond design and cleaning facility)<br />

0%<br />

0%<br />

Detailed Progress<br />

The investigation and membrane fouling analysis to optimise the wastewater plant has been completed; an enhanced (ex-situ)<br />

chemical cleaning process is proposed along with a new (lined) buffer pond. Preliminary design is about to commence with<br />

detailed design expected to be completed by Dec <strong>2013</strong>.<br />

A construction cost estimate based on the concepts developed is $1,200,000 for a new lined pond.<br />

A budget of $900,000 is budgeted for a chemical cleaning plant.<br />

An estimate of $950,000 for membrane capacity expansion (high probability this is not required).<br />

The first site trial was conducted by TDC operations team on 15 May to prove the cleaning concept prior to commitment to<br />

detailed design. The trial is in two parts, a "clean in place' trial and an ex-situ clean trial. Results of the trial are currently being<br />

evaluated. Note: The ex- situ lab trial shown positive results. Once the trials are completed the decision as to which of the<br />

above will be implemented can be made. A new pond will provide long term benefit. The decision regarding chemical, cleaning<br />

plant or membrane capacity expansion or the alternative of do nothing and replace fouled membranes will be made following<br />

the site trials and financial analysis. The preliminary design of the lined buffer pond is completed.<br />

Construction (requirement to be confirmed) is expected to begin in 2014.<br />

Key Risks<br />

Cost estimates are to be remade after the preliminary design. Cost risk is the most significant risk.