What’s New in this <strong>Regional</strong> <strong>Land</strong> <strong>Transport</strong> <strong>Programme</strong><br />
Three region-wide <strong>Land</strong> <strong>Transport</strong> <strong>Programme</strong>s have been produced<br />
by ARTA since being created in 2004. The LTMA 2008 now requires<br />
ARTA to prepare a RLTP, which has a significantly wider focus than<br />
the previous <strong>Auckland</strong> LTP.<br />
The changes to the previous <strong>Auckland</strong> LTPs can be summarised<br />
as follows:<br />
> ARTA has updated its prioritisation process to take account of<br />
the <strong>2009</strong> GPS.<br />
> State highway activities are now included in the ARTA process.<br />
> The RLTP has to include comment on police activities.<br />
In accordance with the widened scope of the RLTP, ARTA has issued<br />
guidelines outlining regional and national priorities for funding,<br />
enabling local authorities and the NZTA (State highways) to submit<br />
appropriate applications to be considered by ARTA for inclusion in<br />
the RLTP.<br />
Following consultation on this first RLTP, ARTA has considered<br />
submissions, amended the document as necessary and approved a<br />
final RLTP, which will be submitted to the NZTA. NZTA will then<br />
consider the RLTP, and prepare a National <strong>Land</strong> <strong>Transport</strong> <strong>Programme</strong><br />
which will allocate funding. Any activity that is not included in the<br />
RLTP may not be included in the NLTP, even if it is a NZTA State<br />
highway project.<br />
><br />
><br />
The RLTP now has a three-year time period.<br />
This RLTP includes packages and groups of linked projects.<br />
As this is a three-year programme and includes State highway<br />
projects, it prioritises over 950 projects, compared to around 300<br />
projects in each of the previous LTPs, as shown in Figure 2.3 below.<br />
Figure 2.3: Number of projects in past <strong>Land</strong> <strong>Transport</strong> <strong>Programme</strong>s compared with the <strong>Regional</strong> <strong>Land</strong> <strong>Transport</strong> <strong>Programme</strong><br />
Number of schemes analysed in the <strong>2009</strong>/10-2011/12 RLTP compared to the 2006/07-2008/09 LTPs<br />
1000<br />
900<br />
800<br />
700<br />
600<br />
Number of activities<br />
500<br />
400<br />
300<br />
200<br />
100<br />
0<br />
2006/07 2007/08 2008/09 <strong>2009</strong>/12<br />
LTP year<br />
6