26.12.2014 Views

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Major Project Summaries 07.<strong>25</strong>.12<br />

Project Project Status Progress from Cost Schedule<br />

Name Description Previous Report Estimate<br />

Camelot <strong>Water</strong><br />

Reclamation<br />

Facility - Phase<br />

1B<br />

DB<br />

Design Engineer: PB <strong>Water</strong>.<br />

Contractor: Encore Construction<br />

The Phase 1B project includes an upgrade<br />

and rehab of existing aeration system and<br />

dissolve oxygen control to allow for<br />

maximization of the existing treatment<br />

capacity and to make the process more<br />

energy efficient; the work includes: upgrade<br />

of the existing blowers; conversion from<br />

Chlorine Gas to Sodium Hypochlorite;<br />

expansion of the chlorine contact tank;<br />

rehabilitation and expansion of the existing<br />

filters; rehab and replacement of the Pine<br />

Island pump station and repair/replace Pine<br />

Island Spray Field distribution system;<br />

addition of a Motor Control Center room, yard<br />

piping and drainage improvements; other<br />

associated modifications.<br />

Phase 1B currently in the<br />

construction phase.<br />

Construction is underway.<br />

Construction on the Chlorine<br />

Contact Tank expansion,<br />

sodium hypochlorite system,<br />

reject pond modifications, filter<br />

effluent piping and other yard<br />

piping, electrical work, and<br />

MCC building is underway.<br />

Phase<br />

1B<br />

Construction GMP is<br />

$5,<strong>25</strong>2,904; Owner<br />

Direct Purchase of<br />

large equipment is<br />

$1,086,298; Biochem<br />

equipment is<br />

$269,742; total<br />

project cost is<br />

$6,598,944.<br />

Construction is<br />

anticipated to be<br />

substantially complete<br />

by February 2013 with<br />

final completion by April<br />

2013.<br />

LS#35 Odor<br />

Control Project<br />

DB<br />

Design Engineer: Webster Environmental<br />

Contractor: To Be Determined<br />

The LS#35 Odor Control project replaces the<br />

existing biological odor control unit to achieve<br />

a more reliable, effective H2S removal rate.<br />

Addition of a second stage biological filter will<br />

more effectively remove organic odors.<br />

Engineering is complete.<br />

The odor control equipment<br />

has been delivered. CMAR<br />

is under contract.<br />

The site design has been<br />

completed and the CMAR<br />

services for the project have<br />

been awarded to Encore<br />

Construction through<br />

competitive bidding. The Odor<br />

Control Equipment has been<br />

delivered. Sub-contractor bids<br />

are due on August 2, <strong>2012</strong>.<br />

Board approval of the<br />

Guaranteed Maximum Price is<br />

anticipated to be requested via<br />

consent agenda at the August<br />

8, <strong>2012</strong> meeting.<br />

Engineer’s<br />

Estimate<br />

Project,<br />

equipment<br />

installation):<br />

$<strong>25</strong>0,000<br />

Equipment<br />

$132,000<br />

Cost<br />

(Total<br />

including<br />

and<br />

cost:<br />

Construction/installation<br />

and start-up of the new<br />

odor control equipment<br />

is anticipated to be<br />

initiated in August and<br />

complete by October<br />

<strong>2012</strong> following the<br />

establishment of<br />

biological colonies in<br />

the biological scrubber<br />

and biological filter.<br />

LS 35 Bypass<br />

Project<br />

LZ<br />

Design Engineer: CPH Engineers, Inc.<br />

CMAR: Encore Construction<br />

The project will construct the force main to<br />

bypass wastewater around Lift Station 35.<br />

Rerouting the force main to bypass LS 35 will<br />

reduce the flow to the lift station.<br />

This project has been<br />

combined with the LS 35<br />

odor control equipment<br />

installation project.<br />

The design has been<br />

completed. CMAR service<br />

bidding has been completed.<br />

The project has been<br />

awarded.<br />

The estimated<br />

construction cost is<br />

$315,000<br />

Construction is<br />

scheduled to be<br />

completed by the end<br />

of October, <strong>2012</strong>.<br />

Walnut WRF<br />

(#3) Digester<br />

Rehabilitation<br />

Design Engineer: CPH Engineers, Inc.<br />

Contractor: To Be Determined<br />

The project will include the rehabilitation of<br />

The consultant has<br />

completed a preliminary cost<br />

and feasibility study of the<br />

rehabilitation options. The<br />

2<br />

Preliminary feasibility and cost<br />

evaluation have been<br />

completed. Revised 90%<br />

design plans were received in<br />

$400,000 (engineer’s<br />

revised preliminary<br />

design cost estimate)<br />

Project will be bid to<br />

CMARs currently under<br />

contract with TWA in<br />

<strong>July</strong><br />

with

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!