July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Major Project Summaries 07.<strong>25</strong>.12<br />
Project Project Status Progress from Cost Schedule<br />
Name Description Previous Report Estimate<br />
DB<br />
Harmony WTP<br />
Miex<br />
Installation<br />
Project<br />
DB<br />
the existing Santaire package plant currently<br />
utilized as a digester including removal of<br />
failing interior walls and inefficient diffuser<br />
heads. The project also includes the<br />
relocation of blowers from Cypress West<br />
WRF that are not in use. The digester is used<br />
as a treatment train when one of the two<br />
Sequencing Batch Reactors (each SBR is<br />
rated for 75% of the 0.84 MGD plant<br />
capacity) is offline for maintenance or repairs<br />
as the plant is near capacity and one SBR<br />
cannot sustain plant flow for extended<br />
periods.<br />
Design Engineer: CH2MHill<br />
Contractor: To Be Determined<br />
This project will install a magnetic ion<br />
exchange system (MIEX) to remove<br />
Dissolved Organic Compounds (DOC) from<br />
the groundwater. The project is necessary to<br />
meet an FDEP Consent Order to reduce<br />
Disinfection By-Products (DBPs) in the<br />
finished water. DBPs, which are formed<br />
when DOCs react with free chlorine, are<br />
regulated under the Safe Drinking <strong>Water</strong> Act.<br />
As an added benefit, the MIEX system will<br />
remove H 2 S; improve smell, taste, and color;<br />
and reduce chlorine demand.<br />
existing Sanitaire Plant will<br />
was to be rehabilitated to<br />
operate as a Sequencing<br />
Batch Reactor (SBR);<br />
however, the anticipated cost<br />
is higher than expected so<br />
the digester will be rehabbed<br />
as is.<br />
Design is underway.<br />
On June 13, <strong>2012</strong> the Board<br />
of Supervisors approved an<br />
addendum with CH2M Hill for<br />
the design, permitting,<br />
bidding and construction<br />
administration services for<br />
the Miex system installation.<br />
On June 15, <strong>2012</strong> the Board<br />
approved staff to proceed<br />
with the design and<br />
installation of a 300 GPM<br />
MIEX unit.<br />
June, <strong>2012</strong> and reviewed by<br />
operations and engineering<br />
staff. Minor revisions are<br />
required and will be complete<br />
by the end of <strong>July</strong>. The<br />
project will be bid to CMARs<br />
currently under contract with<br />
<strong>Toho</strong>.<br />
Negotiations are underway<br />
with Orica (manufacturer of<br />
MIEX) for the Owner Direct<br />
Purchase (ODP) of the MIEX<br />
<strong>Water</strong> Treatment System,<br />
which is a long lead item<br />
(approximately 28 - 32 weeks<br />
for design and fabrication).<br />
The ODP is necessary to<br />
ensure the consent order<br />
schedule is met.<br />
Engineer’s Estimated<br />
Cost of Construction:<br />
$1,300,000<br />
subcontractors bidding<br />
in August. A 6-month<br />
construction period is<br />
estimated.<br />
Design to be complete<br />
by the end of<br />
November <strong>2012</strong>, with<br />
construction beginning<br />
in January 2013. The<br />
project is anticipated to<br />
be complete by the<br />
FDEP Consent Order<br />
deadline of April 2013.<br />
South<br />
Bermuda WRF<br />
Central<br />
Electrical<br />
Building<br />
Engineer: AECOM.<br />
CMAR: Wharton-Smith.<br />
This project will provide a centralized and<br />
reliable backup power supply to serve the<br />
entire South Bermuda <strong>Water</strong> Reclamation<br />
Facility (SBWRF). The existing power backup<br />
system at SBWRF consists of remote<br />
generators dedicated to individual plant<br />
processes. Some of the existing generators<br />
do not have sufficient capacity to supply<br />
power as the processes have been<br />
expanded during previous projects. SBWRF<br />
is a public access reuse facility; therefore<br />
FDEP requires Class 1 reliability for the<br />
electrical system. Class 1 reliability requires<br />
that no single fault or power failure would<br />
disrupt operation of multiple motor control<br />
The central electrical building<br />
and generator work is<br />
substantially complete. The<br />
system is currently in service.<br />
Installation of the lab electric<br />
feeder is 20% complete.<br />
3<br />
The open cut portion of the<br />
electrical conduit is 50%<br />
complete. The directional<br />
bore portion of the conduit<br />
installation is 30% complete.<br />
Once the entire conduit is<br />
installed and the equipment is<br />
delivered, the conductor wires<br />
will be pulled, and the<br />
electrical equipment will be<br />
installed. A 4 week delay is<br />
expected for delivery of the<br />
electrical equipment, due to<br />
product availability and<br />
manufacture lead times.<br />
$462,486<br />
(Engineering Design<br />
& Construction Phase<br />
Services Cost)<br />
$87,660 (CMAR<br />
Preconstruction<br />
Services)<br />
$1,323,333 (Owner<br />
Direct Purchase of<br />
Generators, Fuel<br />
Tanks, Switchgear,<br />
etc.)<br />
$40,175 (Permitting<br />
Fees, by <strong>Toho</strong>)<br />
Construction<br />
August 2011.<br />
initiated<br />
Substantial Completion<br />
issued June <strong>2012</strong>.<br />
Final Completion<br />
(including lab electrical<br />
feeder) scheduled for<br />
September <strong>2012</strong>.