July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Major Project Summaries 07.<strong>25</strong>.12<br />
Project Project Status Progress from Cost Schedule<br />
Name Description Previous Report Estimate<br />
POINCIANA PROJECTS<br />
Poinciana<br />
Gravity Sewer<br />
– Raise<br />
manholes to<br />
grade.<br />
TN<br />
Gravity Sewer<br />
– Repair &<br />
Rehab<br />
Consultant/Contractors:<br />
Bid specification developed by staff.<br />
Manhole raising and rehab to be performed<br />
by Hinterland Group.<br />
Project Description:<br />
The Poinciana’s WWTP#3 collection system<br />
basin was surveyed to identify all buried and<br />
below grade manholes. These manholes<br />
contribute to the Inflow problem in this area<br />
and complicate assessment and operational<br />
maintenance activities. This project will 1)<br />
raise all manholes greater than 8” below<br />
grade and 2) raise all manholes located in<br />
swales or other areas prone to flooding.<br />
Manholes located in the WWTP#2 collection<br />
systems meeting the same criteria as above<br />
are included in this scope.<br />
Consultant/Contractors:<br />
Bid specification for manhole repairs is being<br />
developed by Engineering Technologies<br />
(ET).<br />
Project Description:<br />
Complete rehab and repairs to specified<br />
areas of the gravity sewer collection system.<br />
1. Four high priority areas identified by Field<br />
Services (S. Poinciana & Mercantile,<br />
Lakeside & Boggy Creek, N Old Lake<br />
Wilson & 192, and Formosa Gardens &<br />
192). Repair infiltration and line 67<br />
manholes.<br />
2. The 2010 collection system condition<br />
assessments identified the following for<br />
rehab:<br />
Repair infiltration sources in<br />
manholes (171 manholes)<br />
Rehab or replace manholes with<br />
surface corrosion significant enough<br />
to affect structural integrity (27<br />
All construction activities<br />
including: raising manholes<br />
to grade (224), leak<br />
stoppage (27) and lining<br />
manholes (23) have been<br />
completed.<br />
Final pay application<br />
processed.<br />
Project closed out.<br />
Field inspections completed<br />
by ET on the four areas<br />
identified by Field Services.<br />
Staff has reviewed and<br />
accepted<br />
ET’s<br />
recommendations.<br />
Asset defect and location<br />
information has been<br />
provided to ET for inclusion<br />
in the bid specification.<br />
Staff has completed an initial<br />
review of the bid<br />
specification and has met<br />
with the consultant to provide<br />
feedback.<br />
ET provided a revised Bid<br />
Specification to staff for<br />
review 7/13/12.<br />
Staff review and addition<br />
13<br />
Final pay application<br />
processed.<br />
Project closed out.<br />
Revised Bid Specification<br />
received from ET on 7/13/12.<br />
Total project cost<br />
$201,307.20 resulting<br />
in a surplus of<br />
approximately<br />
$30,0000<br />
Manhole rehab and<br />
repair estimate -<br />
$893,560<br />
Gravity Main rehab<br />
and repair estimate -<br />
$935,000 (based on<br />
replacement cost)<br />
Raise Manholes:<br />
Proposals Due<br />
7/7/11 - Completed<br />
Select apparent low<br />
bidder<br />
7/17/11 - Completed<br />
Obtain Board’s<br />
approval to proceed<br />
7/27/11 - Completed<br />
Field Data Collection<br />
10/<strong>25</strong>/11 - Completed<br />
Raise Manholes<br />
2/28/12 - Completed<br />
Project Close-out<br />
6/21/12 - Completed<br />
Repair/Rehab<br />
Manholes:<br />
Consultant to develop<br />
bid specification for<br />
Repair and Rehab<br />
8/2/12<br />
Advertise Bid<br />
8/3/12<br />
Select apparent low<br />
bidder<br />
9/4/12<br />
Obtain Board’s<br />
approval to proceed<br />
9/26/12