July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Major Project Summaries 07.<strong>25</strong>.12<br />
Project Project Status Progress from Cost Schedule<br />
Name Description Previous Report Estimate<br />
the Buenaventura Lakes WTP; and part of an<br />
overall improvement to the Parkway WTP<br />
distribution system to serve the Springlake<br />
Village service area.<br />
EM<br />
The force main upsizing is necessary to<br />
serve the peak demands of the existing<br />
homes in the area. The existing force<br />
main and pump station system was<br />
constructed prior to the <strong>Authority</strong><br />
purchasing the BVL utility system and is<br />
undersized for the peak flow condition.<br />
SB WRF Lab<br />
Expansion<br />
AG<br />
Architect: KZF Design<br />
Contractor: Welbro-Quinn Constructors<br />
The project will expand the existing<br />
laboratory building at the South Bermuda<br />
WRF 2,000 square feet to include a receiving<br />
and storage room, offices, conference and<br />
support spaces, additional parking, and<br />
minimal landscaping. The existing lab<br />
building was designed for 3 people and there<br />
are currently 6 employees working there. A<br />
trailer is being leased to accommodate the<br />
required office space and support areas.<br />
The expansion of <strong>Toho</strong>’s service areas and<br />
the increased FDEP testing requirements<br />
necessitates additional space for equipment.<br />
Construction is substantially<br />
complete.<br />
The contractor has completed<br />
the floor tile installation and<br />
the millwork, poured the<br />
concrete parking lot and<br />
walkway, and painted the<br />
exterior of the building.<br />
$583,000<br />
(Construction<br />
Contract)<br />
Construction began<br />
March <strong>2012</strong> and will be<br />
substantially complete<br />
by <strong>July</strong> <strong>2012</strong>.<br />
Poinciana Blvd<br />
Ph 3<br />
Engineer: Infrastructure Engineers.<br />
CMAR: Manhattan Construction<br />
Utility Subcontractor: TBD.<br />
This project consists of installing utility<br />
improvements along Poinciana Blvd between<br />
Oren Brown Road and Cumbrian Lakes Drive<br />
in conjunction with the County’s Right-of-Way<br />
improvement project.<br />
The project includes construction of<br />
approximately 1,000 LF of 8” and 12” water<br />
main and 9,400 LF of 20” water main. Also<br />
included are multiple locations where the<br />
existing 20” reuse main is to be diverted to<br />
The final project design has<br />
been revised based on<br />
FDEP, TWA, and CMAR<br />
comments.<br />
FDEP has issued the water<br />
permit.<br />
$187,596<br />
(Engineering, Survey,<br />
SUE, & Geotech<br />
Services)<br />
$1.5M<br />
(Estimated<br />
Construction Cost)<br />
Interlocal Agreement<br />
executed March <strong>2012</strong>.<br />
Design finalized <strong>July</strong><br />
<strong>2012</strong>.<br />
FDEP permit issued<br />
<strong>July</strong> <strong>2012</strong>.<br />
Utility work expected to<br />
be bid <strong>July</strong> <strong>2012</strong>,<br />
dependent on CMAR<br />
schedule.<br />
Substantial Completion<br />
10