Major Project Summaries 07.<strong>25</strong>.12<br />
Project Project Status Progress from Cost Schedule<br />
Name Description Previous Report Estimate<br />
EM<br />
Osceola<br />
Parkway<br />
(from<br />
Buenaventura<br />
Blvd. to<br />
Boggy Creek<br />
Rd.)<br />
proposed roadway construction.<br />
With the completed phases 1 and 2 the 16"<br />
water main will extend from Central Avenue<br />
to Dyer Boulevard providing a loop system<br />
that will increase system pressures in the<br />
southern portions of the City area; improve<br />
service to the area south with pressure<br />
issues (i.e., Brighton Lakes, The Oaks, Good<br />
Samaritan Village); and provide water service<br />
to vacant parcels along the roadway corridor.<br />
The sewer extension will provide sewer<br />
service to approximately 7 to 10 vacant<br />
parcels. The exact amount of parcels is<br />
currently unknown. These parcels and the<br />
City's proposed landscaped median will<br />
benefit from the existing 30” reuse main. The<br />
existing sewer pipe requires rehabilitation<br />
due to the condition and age of the<br />
infrastructure.<br />
Design Engineer: CPH Engineers<br />
Contractor: To Be Determined<br />
The project consists of the extension of<br />
approximately 11,200 lineal feet of 24” water<br />
main; relocation/upsizing of 2,900 lineal feet<br />
of 6” force main to 8”; and relocation of an<br />
estimated 300 lineal feet of 6” force main.<br />
The project’s construction has been split<br />
in two. One portion will construct the<br />
new 8” force main ahead of the roadway<br />
improvements. The second portion will<br />
construct the 24” water main and the<br />
miscellaneous force main relocations in<br />
conjunction with Osceola County’s roadway<br />
improvements.<br />
The water main extension is required to<br />
provide the prescribed level of service to the<br />
area now served by the offline Springlake<br />
Village WTP; (to eventually be<br />
decommissioned); interconnecting the<br />
Buenaventura Lakes subdivision with the<br />
Eastern Regional <strong>Water</strong> System (<strong>Toho</strong> 1)<br />
allowing for the eventual decommissioning of<br />
potential debris along the<br />
path of the proposed water<br />
and sewer utilities.<br />
Force main construction is<br />
currently underway.<br />
CPH has completed<br />
100% design on the 24”<br />
water main and<br />
miscellaneous force main<br />
relocations.<br />
A pre-bid meeting for the<br />
water main and other<br />
miscellaneous utility<br />
relocations is scheduled<br />
for 7/20/12.<br />
9<br />
Force main construction is<br />
approximately <strong>25</strong>%<br />
complete.<br />
<strong>Water</strong> main and other<br />
miscellaneous design plans<br />
have been submitted to<br />
Osceola County for<br />
bidding.<br />
Force Main<br />
Upsizing Low Bid =<br />
$184,385.00<br />
<strong>Water</strong> Main and<br />
Miscellaneous<br />
Force Main<br />
Relocations =<br />
$1,800,000 (90%<br />
Design Estimate)<br />
Force Main<br />
construction currently<br />
underway.<br />
<strong>Water</strong> Main<br />
construction is<br />
scheduled to start by<br />
the end of<br />
September <strong>2012</strong>.