26.12.2014 Views

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

GE<br />

Major Project Summaries 07.<strong>25</strong>.12<br />

Project Project Status Progress from Cost Schedule<br />

Name Description Previous Report Estimate<br />

ROW. These efforts account for 29% of the<br />

utility contract amount.<br />

Hoagland Blvd.<br />

Segment 1<br />

<strong>Water</strong> Main &<br />

Sewer Main<br />

Relocation and<br />

Reuse Main<br />

Addition<br />

LZ<br />

Design Engineer: Hanson Walter Associates<br />

Contractor: Jr. Davis Construction Company<br />

The Hoagland Blvd. Segment 1 project will<br />

adjust the existing 16" water main and two<br />

existing force mains (6" and 20") to<br />

accommodate the County roadway widening<br />

project from US-192 to 5th street. In addition<br />

to the adjustments, a new 16-inch reuse<br />

main will be constructed. This project is a<br />

cooperative effort between the County and<br />

TWA and the utility work will be constructed<br />

in conjunction with the roadway project.<br />

All water main deflections,<br />

force main, and reuse main<br />

installation have been<br />

completed. The 6" force main<br />

has been removed. The 20"<br />

force main removal is<br />

underway. Utility construction<br />

is approximately 95%<br />

completed.<br />

Reuse main installation has<br />

been completed.<br />

The low bid price for<br />

utility work is<br />

$1,214,249.50.<br />

The project completion<br />

date has been<br />

extended to September<br />

<strong>2012</strong> by County due to<br />

the addition of roadway<br />

work. Utility work is<br />

scheduled to be finally<br />

completed by<br />

September <strong>2012</strong>.<br />

Reuse WM<br />

System<br />

Improvements<br />

AG<br />

Design Engineer: CPH<br />

Contractor: Wright’s Excavating<br />

Extension of reuse water mains to developed<br />

areas that have reuse infrastructure but are<br />

connected to potable water. Line extension<br />

projects have been identified that will connect<br />

the following developments to TWA’s reuse<br />

system: Country Crossing, VoTech,<br />

Westminster Gardens, and Windward Cay.<br />

The pre-construction meeting<br />

will be scheduled by the end<br />

of <strong>July</strong>.<br />

Connection of the Indian<br />

Point, Eagle Point, Lake<br />

Brantley Resort, Cumbrian<br />

Lakes, Liberty Village and<br />

Bellavida Phase 2 has been<br />

delayed to construct the<br />

reuse main in conjunction<br />

with the County’s delayed<br />

Poinciana Blvd. Road<br />

Improvements project.<br />

The construction contract was<br />

awarded to Wright’s<br />

Excavating and the Notice of<br />

Award documents were<br />

distributed.<br />

The engineering<br />

design contract is<br />

$90,320.00 and the<br />

construction contract<br />

is $503,091.<br />

The construction phase<br />

began <strong>July</strong> <strong>2012</strong> and<br />

has a construction<br />

duration of 6 months.<br />

Osceola<br />

Parkway –<br />

Florida<br />

Turnpike <strong>Water</strong><br />

Main Crossing<br />

Design Engineer: CPH Engineers<br />

Contractor: To Be Determined<br />

The project consists of the extension of<br />

approximately 2,000 lineal feet of 24” water<br />

main directional bored or jack and bored<br />

under the Florida Turnpike. The main will<br />

connect the <strong>Toho</strong> I system with the newly<br />

constructed <strong>Toho</strong> III water main on Osceola<br />

Parkway.<br />

The water main extension is required to<br />

provide the prescribed level of service to the<br />

area now served by the offline Springlake<br />

Village WTP; (to eventually be<br />

decommissioned); interconnecting the<br />

Buenaventura Lakes subdivision with the<br />

CPH Engineers has made<br />

several attempts to schedule<br />

a meeting with the Turnpike<br />

<strong>Authority</strong> to determine their<br />

design requirements for<br />

crossing the Turnpike. Once<br />

these requirements are<br />

known, CPH will finalize the<br />

scope of design services.<br />

7<br />

CH2M Hill has completed their<br />

hydraulic analysis to<br />

determine the minimum pipe<br />

size required to interconnect<br />

the TOHO I and TOHO III<br />

water systems. The minimum<br />

pipe size required is a 16”<br />

pipe.<br />

Design will be finalized and<br />

constructed in the next dry<br />

season (between December<br />

<strong>2012</strong> and May 2013.<br />

$1,800,000 (Predesign<br />

Estimate)<br />

Staff will develop a<br />

schedule upon<br />

completion of CPH’s<br />

scope.<br />

Funds are proposed for<br />

Fiscal Year <strong>2012</strong>-13.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!