26.12.2014 Views

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

July 25, 2012 - Toho Water Authority

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

EM<br />

Major Project Summaries 07.<strong>25</strong>.12<br />

Project Project Status Progress from Cost Schedule<br />

Name Description Previous Report Estimate<br />

A scope amendment was approved for the<br />

design of water services and stub-outs to<br />

existing vacant properties and properties<br />

currently on well water.<br />

This work will allow the decommissioning of<br />

the existing Pleasant Hill Lakes WTP<br />

previously owned by O&S Services & will<br />

interconnect the Eastern Regional <strong>Water</strong><br />

System with Poinciana WTP #6.<br />

information requested by the<br />

FDEP and will submit by<br />

7/20/12.<br />

Old Lake<br />

Wilson Road<br />

Widening<br />

Engineer: HWA.<br />

CMAR: WG Mills, Inc. / Ranger Building<br />

Services, Inc., a Joint Venture.<br />

Utility Subcontractor: Wright’s Excavating<br />

This project consists of utility relocations<br />

along Old Lake Wilson Road between<br />

Westgate Boulevard and Sinclair Road in<br />

conjunction with the County’s road widening<br />

project. This project also includes a 12” and<br />

16” reuse main along Old Lake Wilson Road<br />

between Livingston Road and Sinclair Road<br />

and a reuse connection at Livingston Road<br />

and Sand Hill Road. The reuse<br />

improvements will provide 0.2 MGD of reuse<br />

to existing developments along the<br />

Livingston and Old Lake Wilson Road<br />

corridors. Reuse demand within the<br />

corridors will increase to approximately 1.2<br />

MGD as the area is further developed.<br />

The utility improvements include: 2,700 LF of<br />

30” water main (WM), 2,600 LF of 24” WM,<br />

800 LF of 16” 12” and 8” WM, 1,200 LF of<br />

16” reuse main (RM), 12,500 LF of 12” RM,<br />

4,300 LF of 30” force main (FM), 2,400 LF of<br />

8” FM, and 700 LF of 12” 10” and 6” FM.<br />

The utility portion of the<br />

project is substantially<br />

complete, pending submittal<br />

of the Substantial Completion<br />

form by the CMAR and<br />

FDEP water main clearance.<br />

The utility contractor is<br />

currently completing punchlist<br />

items generated on the<br />

substantial completion<br />

walkthrough.<br />

Final wastewater permit<br />

clearance has been received.<br />

Final water permit clearance<br />

application has been<br />

submitted to FDEP.<br />

Design Contract:<br />

$226,800 (Total)<br />

$161,000 (TWA<br />

Share)<br />

$ 65,800 (County<br />

Share)<br />

Utility Construction<br />

Contract (including<br />

CMAR fees, CEI<br />

services, materials<br />

testing, insurance,<br />

bonds, &<br />

contingency):<br />

$4,467,900 (Total)<br />

$3,172,200 (TWA<br />

Share)<br />

$1,295,700 (County<br />

Share)<br />

$33,912 (County<br />

share of Change<br />

Orders)<br />

$161,494 (TWA<br />

share of Change<br />

Orders)<br />

Utility bids opened<br />

February 15, 2010.<br />

Interlocal Agreement<br />

recorded June 28,<br />

2010.<br />

Utility Substantial<br />

Completion expected<br />

<strong>July</strong> <strong>2012</strong>.<br />

Utility Final Completion<br />

scheduled August<br />

<strong>2012</strong>.<br />

This work is to be constructed under the<br />

<strong>Toho</strong> <strong>Water</strong> <strong>Authority</strong>/Osceola County<br />

interlocal agreement recorded June 28,<br />

2010. The agreement stipulates that County<br />

is to reimburse TWA for relocation of all<br />

mains currently located within easements<br />

affected by the acquisition of additional<br />

6

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!