July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
EM<br />
Major Project Summaries 07.<strong>25</strong>.12<br />
Project Project Status Progress from Cost Schedule<br />
Name Description Previous Report Estimate<br />
A scope amendment was approved for the<br />
design of water services and stub-outs to<br />
existing vacant properties and properties<br />
currently on well water.<br />
This work will allow the decommissioning of<br />
the existing Pleasant Hill Lakes WTP<br />
previously owned by O&S Services & will<br />
interconnect the Eastern Regional <strong>Water</strong><br />
System with Poinciana WTP #6.<br />
information requested by the<br />
FDEP and will submit by<br />
7/20/12.<br />
Old Lake<br />
Wilson Road<br />
Widening<br />
Engineer: HWA.<br />
CMAR: WG Mills, Inc. / Ranger Building<br />
Services, Inc., a Joint Venture.<br />
Utility Subcontractor: Wright’s Excavating<br />
This project consists of utility relocations<br />
along Old Lake Wilson Road between<br />
Westgate Boulevard and Sinclair Road in<br />
conjunction with the County’s road widening<br />
project. This project also includes a 12” and<br />
16” reuse main along Old Lake Wilson Road<br />
between Livingston Road and Sinclair Road<br />
and a reuse connection at Livingston Road<br />
and Sand Hill Road. The reuse<br />
improvements will provide 0.2 MGD of reuse<br />
to existing developments along the<br />
Livingston and Old Lake Wilson Road<br />
corridors. Reuse demand within the<br />
corridors will increase to approximately 1.2<br />
MGD as the area is further developed.<br />
The utility improvements include: 2,700 LF of<br />
30” water main (WM), 2,600 LF of 24” WM,<br />
800 LF of 16” 12” and 8” WM, 1,200 LF of<br />
16” reuse main (RM), 12,500 LF of 12” RM,<br />
4,300 LF of 30” force main (FM), 2,400 LF of<br />
8” FM, and 700 LF of 12” 10” and 6” FM.<br />
The utility portion of the<br />
project is substantially<br />
complete, pending submittal<br />
of the Substantial Completion<br />
form by the CMAR and<br />
FDEP water main clearance.<br />
The utility contractor is<br />
currently completing punchlist<br />
items generated on the<br />
substantial completion<br />
walkthrough.<br />
Final wastewater permit<br />
clearance has been received.<br />
Final water permit clearance<br />
application has been<br />
submitted to FDEP.<br />
Design Contract:<br />
$226,800 (Total)<br />
$161,000 (TWA<br />
Share)<br />
$ 65,800 (County<br />
Share)<br />
Utility Construction<br />
Contract (including<br />
CMAR fees, CEI<br />
services, materials<br />
testing, insurance,<br />
bonds, &<br />
contingency):<br />
$4,467,900 (Total)<br />
$3,172,200 (TWA<br />
Share)<br />
$1,295,700 (County<br />
Share)<br />
$33,912 (County<br />
share of Change<br />
Orders)<br />
$161,494 (TWA<br />
share of Change<br />
Orders)<br />
Utility bids opened<br />
February 15, 2010.<br />
Interlocal Agreement<br />
recorded June 28,<br />
2010.<br />
Utility Substantial<br />
Completion expected<br />
<strong>July</strong> <strong>2012</strong>.<br />
Utility Final Completion<br />
scheduled August<br />
<strong>2012</strong>.<br />
This work is to be constructed under the<br />
<strong>Toho</strong> <strong>Water</strong> <strong>Authority</strong>/Osceola County<br />
interlocal agreement recorded June 28,<br />
2010. The agreement stipulates that County<br />
is to reimburse TWA for relocation of all<br />
mains currently located within easements<br />
affected by the acquisition of additional<br />
6