Consent<br />

Contract Change Order<br />

ADDITION OF THE LIFT STATION #<strong>25</strong>B FORCE MAIN EXTENSION PROJECT TO STRICKLER<br />

BROTHER’S EXISTING LIFT STATION #21B REHAB PROJECT<br />

Explanation: On May 23 rd , the Board approved the Osceola Parkway Force Main construction contract<br />

with Jr. Davis that upsizes approximately 2,900 feet of 6” force main to 8” force main from Lift Station <strong>25</strong>B<br />

to the start of the Osceola Parkway Phase 2 Road widening project. This project extends the force main<br />

1,200 feet to the downstream master lift station, which is currently under contract with Strickler Brothers<br />

for rehabilitation.<br />

This force main extension is needed because the existing 8” gravity sewer system receiving the flow from<br />

the existing 6” force main (to be upsized to 8”), is undersized to accommodate the peak flows from the<br />

surrounding area as evidenced by surcharging at the 6” force main discharge manhole. The rehabilitation<br />

of LS-<strong>25</strong>B, to be constructed upon completion of the force main extension, will upsize the pumps to meet<br />

current flows. The pump upsizing and increased flow will further exacerbate the surcharging problem if<br />

this force main extension is not implemented. These force main upsizing and extension projects are<br />

needed to provide additional capacity, reduce the probability of sewer spills, and also decrease energy<br />

consumption and operational costs through reduced pump run times.<br />

This project must be completed prior to Phase 2 of the County’s Osceola Parkway Road Widening project<br />

that is scheduled to begin construction this October in order to avoid additional costs associated with the<br />

roadway construction. Strickler Brothers, as low bidder, is currently under contract with TWA to rehab LS-<br />

21B, which is at the downstream tie-in point of this force main extension.<br />

Staff has negotiated a price of $108,<strong>25</strong>0.00 with Strickler Brothers to construct the 1,200-foot force main<br />

extension as an addition to their existing contract. Strickler Brother’s pricing is consistent with their low<br />

bid unit prices from their LS-21B Rehab project; i.e. their unit price for directional drilling 800 feet of 12”<br />

force main was $54 per foot and their unit price for this project’s 1,200 feet of 10” force main is $52 per<br />

foot. The price difference is reflective of the pipe material cost and the level of difficulty to perform longerlength<br />

directional drills.<br />

Staff requests a 10% construction contingency for this project.<br />

This project will be funded by budgeted sewer system rehabilitation funds, project #31200.<br />

RECOMMENDATION: Staff recommends approval of the LS-<strong>25</strong>B Force Main Extension Change Order<br />

to Strickler Brother’s existing Lift Station Rehab project in the amount of $108,<strong>25</strong>0, and a 10%<br />

construction contingency of $10,8<strong>25</strong>.<br />

LS-<strong>25</strong>B FM Extension-07.<strong>25</strong>.12.ag<br />