July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
July 25, 2012 - Toho Water Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Category:<br />
Attachment(s):<br />
Consent<br />
Contract Change Order<br />
ADDITION OF THE LIFT STATION #<strong>25</strong>B FORCE MAIN EXTENSION PROJECT TO STRICKLER<br />
BROTHER’S EXISTING LIFT STATION #21B REHAB PROJECT<br />
Explanation: On May 23 rd , the Board approved the Osceola Parkway Force Main construction contract<br />
with Jr. Davis that upsizes approximately 2,900 feet of 6” force main to 8” force main from Lift Station <strong>25</strong>B<br />
to the start of the Osceola Parkway Phase 2 Road widening project. This project extends the force main<br />
1,200 feet to the downstream master lift station, which is currently under contract with Strickler Brothers<br />
for rehabilitation.<br />
This force main extension is needed because the existing 8” gravity sewer system receiving the flow from<br />
the existing 6” force main (to be upsized to 8”), is undersized to accommodate the peak flows from the<br />
surrounding area as evidenced by surcharging at the 6” force main discharge manhole. The rehabilitation<br />
of LS-<strong>25</strong>B, to be constructed upon completion of the force main extension, will upsize the pumps to meet<br />
current flows. The pump upsizing and increased flow will further exacerbate the surcharging problem if<br />
this force main extension is not implemented. These force main upsizing and extension projects are<br />
needed to provide additional capacity, reduce the probability of sewer spills, and also decrease energy<br />
consumption and operational costs through reduced pump run times.<br />
This project must be completed prior to Phase 2 of the County’s Osceola Parkway Road Widening project<br />
that is scheduled to begin construction this October in order to avoid additional costs associated with the<br />
roadway construction. Strickler Brothers, as low bidder, is currently under contract with TWA to rehab LS-<br />
21B, which is at the downstream tie-in point of this force main extension.<br />
Staff has negotiated a price of $108,<strong>25</strong>0.00 with Strickler Brothers to construct the 1,200-foot force main<br />
extension as an addition to their existing contract. Strickler Brother’s pricing is consistent with their low<br />
bid unit prices from their LS-21B Rehab project; i.e. their unit price for directional drilling 800 feet of 12”<br />
force main was $54 per foot and their unit price for this project’s 1,200 feet of 10” force main is $52 per<br />
foot. The price difference is reflective of the pipe material cost and the level of difficulty to perform longerlength<br />
directional drills.<br />
Staff requests a 10% construction contingency for this project.<br />
This project will be funded by budgeted sewer system rehabilitation funds, project #31200.<br />
RECOMMENDATION: Staff recommends approval of the LS-<strong>25</strong>B Force Main Extension Change Order<br />
to Strickler Brother’s existing Lift Station Rehab project in the amount of $108,<strong>25</strong>0, and a 10%<br />
construction contingency of $10,8<strong>25</strong>.<br />
LS-<strong>25</strong>B FM Extension-07.<strong>25</strong>.12.ag<br />
7B