VICTORIA PARK COMPREHENSIVE MASTER PLAN<br />
5.9<br />
Waterfront Matrix<br />
Zone Facility Intention Timeframe Objective Task Frequency<br />
Waterfront<br />
Boardwalk<br />
Upgrade existing boardwalk to a multimodal<br />
facility.<br />
Raise boardwalk level along with sea wall<br />
improvements<br />
Widen boardwalk cross section to 4.0 - 5.0 metres<br />
Short Term<br />
Investment Upgrade surfacing from wood to hard surface<br />
Medium - Long<br />
Term<br />
Investment<br />
Explore the feasibility <strong>of</strong> permeable paving<br />
Raise height and improve construction <strong>of</strong> sea wall<br />
Construct 4.0 - 5.0 m wide boardwalk<br />
Narrow travel lanes to 3.2m width<br />
Increase medians and add other traffic calming measures<br />
<strong>Park</strong> Road Convert to an internal park carriageway. Short Term Investment<br />
Change surfacing at key gateways & crossings<br />
Look -<strong>of</strong>fs & Water Access<br />
Sea wall<br />
Create a series <strong>of</strong> safe water access points<br />
and look-<strong>of</strong>fs<br />
Maintain the existing sea wall<br />
Upgrade the sea wall to account for sea<br />
level rise & major storm events.<br />
<strong>Re</strong>duce speed limit.<br />
<strong>Re</strong>move civic street name<br />
Medium Term Investment Promote enhanced access and connection to the water.<br />
Ongoing<br />
<strong>Re</strong>gular<br />
Maintenance<br />
Inspect the sea wall for damage, top up armour stone as<br />
required.<br />
Long Term Investment Upgrade the height and construction <strong>of</strong> the existing sea wall.<br />
Annually and after any major events.<br />
5.10<br />
Heritage & Cultural Matrix<br />
Zone Facility Intention Timeframe Objective Task Frequency<br />
Heritage &<br />
Culture<br />
Fort Edward Battery<br />
Memorials & Public Art<br />
Signage and Interpretation<br />
Maintain character and quality <strong>of</strong> Fort<br />
Inspect artifacts and installations for damage and wear. Bi-annually<br />
Ongoing<br />
Edward’s historic assets<br />
<strong>Re</strong>gular<br />
<strong>Re</strong>move graffiti and vandalism<br />
Within 24 hours <strong>of</strong> incident.<br />
Maintain existing interpretive signage Ongoing<br />
Maintenance Inspect panels, footings, and base for wear. Annually<br />
<strong>Re</strong>pair as required.<br />
As needed<br />
Update and add to existing interpretive Medium Term<br />
Add to the quality and quantity <strong>of</strong> the interpretation at Fort<br />
Investment<br />
signage<br />
Edward<br />
Maintain existing memorials and public art<br />
<strong>Re</strong>gular<br />
Inspect memorials for damage and wear.<br />
Bi-annually<br />
Ongoing<br />
installations.<br />
Maintenance <strong>Re</strong>move graffiti and vandalism Within 24 hours <strong>of</strong> incident.<br />
Maintain existing memorials and public art<br />
installations.<br />
<strong>Re</strong>gular<br />
Inspect memorials for damage and wear.<br />
Bi-annually in the fall and spring.<br />
Ongoing<br />
Maintenance <strong>Re</strong>move graffiti and vandalism Within 24 hours <strong>of</strong> incident.<br />
Install new signage Short Term Investment Install new park signage, as required<br />
55