Reason: Required to be imposed pursuant to Section 91 (as amended) of the Town and Country<br />
<strong>Planning</strong> Act 1990.<br />
2 The development hereby permitted shall not be carried out otherwise than in strict accordance<br />
with the submitted details.<br />
Reason: For the avoidance of doubt and to define the permission.<br />
3 Prior to the commencement of the development hereby approved details of the cross-sections of<br />
the windows frames and rainwater goods shall be submitted to and approved in writing by the local<br />
planning authority. The development shall be constructed in accordance with the approved details<br />
to the satisfaction of the local planning authority.<br />
Reason: Inadequate details of these matters have been submitted with this application and in the<br />
interests of the visual amenities of the locality in order to comply with Policy E10 of the <strong>Hyndburn</strong><br />
<strong>Borough</strong> Local Plan.<br />
4 No development approved by this permission shall be commenced until the application site has<br />
been subjected to a detailed investigation and recording of all potential contamination. The<br />
proposed methodology of the survey shall be submitted to and approved in writing by the local<br />
planning authority before any work commences. The findings of the survey shall be submitted to<br />
the local planning authority, together with full details of any de-contamination work proposed to<br />
deal with any contamination found by the survey. No work shall commence on site until all work<br />
to secure the de-contamination of the site to a condition suitable for its future use has been carried<br />
out to the satisfaction of the local planning authority and confirmed in writing as being completed.<br />
Reason: To safeguard the health of the future occupants of the land in the interests of public health<br />
and in order to comply with Policies E2, E10 and E13 of the <strong>Hyndburn</strong> <strong>Borough</strong> Local Plan.<br />
5 The proposed development is near to a former landfill site. Therefore a ground slab and gas<br />
proof membrane of minimum 1200g thickness shall be incorporated into the foundations in order to<br />
provide adequate protection against the ingress of landfill gas. The membrane shall be:<br />
i. laid carefully so as to avoid tears or perforations<br />
ii. well-lapped and taped at the joints and<br />
iii. continuous across the whole area of the new development<br />
Reason: In the interests of safety having regard to the proximity of the site to a former landfill site<br />
and in order to comply with Policies E2 and E10 of the <strong>Hyndburn</strong> <strong>Borough</strong> Local Plan.<br />
6 Prior to the commencement of the development hereby approved, samples of the external<br />
roofing and facing materials shall be submitted to and approved in writing by the local planning<br />
authority. The development shall be constructed in accordance with the approved details/samples.<br />
Reason: To ensure the use of appropriate materials, in the interests of the visual amenities of the<br />
locality and in order to comply with Policy E10 of the <strong>Hyndburn</strong> <strong>Borough</strong> Local Plan.<br />
7 Notwithstanding Article 3 of the Town and Country <strong>Planning</strong> (General Permitted Development)<br />
Order 1995 no development shall take place within the curtilage of the dwelling hereby approved in<br />
accordance with Classes A, B, C, D, E, F, G, or H of part 1 of Schedule 2, unless a planning<br />
application for that development has been submitted to and approved by the local planning<br />
authority.<br />
57