REQUEST FOR BOARD ACTION<br />
Agenda: 11-16<br />
Subject: Authorization for Mayor to Sign Addendum to Intergovernmental Agreement for<br />
Wilmot Road Infrastructure Rehabilitation<br />
Action Requested Authorize Mayor to Sign Agreement<br />
Originated By: Engineering Department<br />
Referred To: Mayor and Board <strong>of</strong> Trustees<br />
Summary <strong>of</strong> Background and Reason for Request:<br />
In December, 2007 the <strong>Village</strong> <strong>of</strong> <strong>Deerfield</strong> Board <strong>of</strong> Trustees approved an Intergovernmental Agreement (IGA)<br />
with the Illinois State Toll Highway Authority (ISTHA) and the Cook County Highway Department (CCHD) to<br />
coordinate the construction <strong>of</strong> the improvements at the intersection <strong>of</strong> Wilmot Road, Lake Cook Road and I-294.<br />
Work that was performed as part <strong>of</strong> the project included reconstruction <strong>of</strong> the bridge over the northbound lanes <strong>of</strong><br />
the Tri-State Tollway (I-294) to accommodate the widening <strong>of</strong> the Tollway, resurfacing about ¾ <strong>of</strong> a mile <strong>of</strong> Lake<br />
Cook Road from west <strong>of</strong> the southbound I-294 entrance and exit ramps to east <strong>of</strong> Wilmot Road, and water main<br />
construction and resurfacing along Wilmot Road.<br />
You may recall that the Lake Cook Road Bridge Replacement and Roadway Widening Project was a joint effort<br />
between the Cook County Highway Department, the Illinois Tollway, and the <strong>Village</strong> <strong>of</strong> Deefield to improve travel,<br />
reduce impact on motorists along the Tollway, and improve traffic operations along Wilmot Road. The project was<br />
part <strong>of</strong> the Illinois Tollway’s North Tri-State Tollway (I-294/94) Rebuild & Widen Project to provide congestion<br />
relief. The original IGA was signed by the CCHD, ISTHA and the <strong>Village</strong> <strong>of</strong> <strong>Deerfield</strong>. The IGA outlined the<br />
financial responsibilities <strong>of</strong> each party. The IGA was executed by all parties and is dated January 31, 2008.<br />
The CCHD has requested an addendum to the IGA due to cost increases with respect to utility relocation. The<br />
Tollway covered those expenses to expedite the work. The additional costs must be presented to the County Board in<br />
order to fully reimburse the Tollway. The <strong>Village</strong> <strong>of</strong> <strong>Deerfield</strong> has fulfilled its financial obligation and no further<br />
reimbursement for this contract is required. The reason this document impacts the <strong>Village</strong> is because the <strong>Village</strong> was<br />
signatory to the original agreement. The County has verbally approved this addendum and the Tollway is now<br />
asking us for approval. This is the second addendum to the IGA, the first being approved by the Board <strong>of</strong> Trustees<br />
in September <strong>of</strong> 2010.<br />
The Director <strong>of</strong> Public Works and Engineering recommends that the Board <strong>of</strong> Trustees authorize the Mayor to<br />
execute the Intergovernmental Agreement Addendum # 2. A copy <strong>of</strong> the agreement is attached for your reference.<br />
Reports and Documents Attached<br />
Copy <strong>of</strong> Agreement<br />
Date Referred to Board: February 7, 2011<br />
Action Taken: ________________________________________