Report on Departmental Objectives<br />

February 3, 2011<br />

Page 8<br />

Reline approximately 3,500 lineal feet <strong>of</strong> sewers – Sewer Department is working in conjunction with<br />

engineering to line the sewers on Pine and Hackberry as part <strong>of</strong> the Waste Water Treatment Plant<br />

reconstruction project.<br />

The Sewer Department continues to work with RJN Group and has begun to implement the<br />

recommendations to reduce the inflow and infiltration into the sanitary sewer system by lining sewers and<br />

repairing leaking manholes that have been identified. Additionally, the <strong>Village</strong> has submitted an<br />

application to the Illinois Environmental Protection Agency for an Illinois Green Infrastructure Grant<br />

(IGIG) to assist the <strong>Village</strong> in setting up a program that would provide funding to assist homeowner in<br />

removing their sump pumps from the sanitary sewer system.<br />

Public<br />

Sector<br />

Work with the Engineering Department on the design <strong>of</strong> various projects – The Department assisted<br />

with the 2010 Street Rehabilitation Program and the Carlisle / Carriageway Infrastructure Project.<br />

Ongoing Activities – Routine daily activities include JULIE (Joint Utility Locating Information for<br />

Excavators) locates, sewer cleaning, sewer televising, responding to sewer backups, flooding, and drainage<br />

issues.<br />

GARAGE DEPARTMENT<br />

Manholes<br />

Cross Connections<br />

Typical Defect Distribution<br />

Mainlines<br />

Laterals<br />

Sump Pumps<br />

Foundation<br />

Drains/Area Drains<br />

Private Sector<br />

Garage personnel, consisting <strong>of</strong> one foreman and one mechanic are responsible for the overall<br />

maintenance <strong>of</strong> all public works, police and engineering vehicles and equipment. This includes repair and<br />

maintenance <strong>of</strong> 10 administration cars, 18 police-related cars, 27 public works vehicles, and 93 various<br />

pieces <strong>of</strong> construction and maintenance related equipment. The equipment includes 25 snow plows, 3<br />

backhoes, 2 front end loaders, 2 mower tractors, 3 Bobcats, 1 sidewalk plow, 5 snow blowers (2 machine<br />

mounted and 4 walk behind), 1 street sweeper, three 20-cubic yard self-loading leaf vacuum trailers, one<br />

14-cubic yard self-loading leaf vacuum trailer, 1 lighting trailer, 4 air compressors, 8 salt spreaders, 6