29.01.2013 Views

02.07.2011 - Village of Deerfield

02.07.2011 - Village of Deerfield

02.07.2011 - Village of Deerfield

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

REQUEST FOR BOARD ACTION<br />

Agenda Item: 11-14<br />

Subject: Authorization for Additional Work for the Carlisle Avenue and Carriage Way<br />

Infrastructure Rehabilitation Project<br />

Action Requested: Authorize Additional Work for the project ($400,000)<br />

Originated By: Director <strong>of</strong> Public Works and Engineering<br />

Referred To: Mayor and Board <strong>of</strong> Trustees<br />

Summary <strong>of</strong> Background and Reason for Request:<br />

As a result <strong>of</strong> the May 3, 2010 bid opening, the Department <strong>of</strong> Public Works and Engineering awarded the construction<br />

contract for the Carlisle Avenue and Carriage Way Infrastructure Rehabilitation Project. The project limits are Carlisle<br />

Avenue from the Briarwood Nature Area to <strong>Deerfield</strong> Road and Carriage Way from the Briarwood Nature Area to Bent<br />

Creek Ridge. The scope <strong>of</strong> work includes roadway removal and replacement, water main replacement, drainage<br />

improvements, and intermittent sidewalk removal and replacement. The contract was awarded to Bolder Contractors,<br />

Inc., the low bidder with a bid price <strong>of</strong> $3,762,918.98. The project spans two construction seasons from 2010-2011.<br />

At the close <strong>of</strong> the first construction season Carlisle Avenue between the Briarwood Nature Area and <strong>Deerfield</strong> Road, is<br />

substantially complete. Though the project timing was slightly impacted by a labor union strike, and removal <strong>of</strong> large<br />

quantities <strong>of</strong> unsuitable sub-grade material, the <strong>Village</strong> and the contractor were able to meet a revised completion date <strong>of</strong><br />

November 15, 2010. The work that was completed during the first construction season included more than 3,500 linear<br />

feet <strong>of</strong> newly constructed pavement, 600 linear feet <strong>of</strong> new 5’ wide sidewalk, 2,000 linear feet <strong>of</strong> storm sewer, 5,000<br />

linear feet <strong>of</strong> water main, a new lighting system along Carlisle Avenue, and one storm sewer collection and filtration unit.<br />

The nature <strong>of</strong> infrastructure reconstruction projects <strong>of</strong>ten consist <strong>of</strong> work items, or exact quantities, that are not easily<br />

identified during the design process. Unforeseen conditions <strong>of</strong>ten require additional quantities for work items to be<br />

performed or may require the engineer to request agreed unit prices for work items that are not part <strong>of</strong> the original<br />

contract. The Carlisle Avenue and Carriage Way Infrastructure project is not an exception. The condition <strong>of</strong> existing<br />

utilities just outside <strong>of</strong> the project limits and worse than expected soil conditions will have an overall impact on the<br />

budget for the project, causing the project as a whole to exceed the awarded amount by nearly 11%.<br />

At the close <strong>of</strong> the 2010 construction season staff and the contractor met to review all completed work items to determine<br />

the remaining budget for the next phase, Carriage Way between the Briarwood Nature Area and Bent Creek Ridge. As a<br />

result <strong>of</strong> our discussions, we have determined that it is not possible for the project to be completed within the contract<br />

amount if removal and replacement <strong>of</strong> unsuitable sub-grade material is required as expected, based on the experience<br />

with Carlisle. Therefore, staff has estimated the amount <strong>of</strong> additional work that will be required to complete the project<br />

and recommends increasing the contract by $400,000.<br />

The Director <strong>of</strong> Public Works and Engineering recommends that the Mayor and Board <strong>of</strong> Trustees authorize the<br />

additional expenditure to complete the remainder <strong>of</strong> the Carlisle Avenue and Carriage Way Infrastructure Rehabilitation<br />

Project, increasing the total contract amount from the base bid <strong>of</strong> $3,762,918.98 to $4,162,918.98.<br />

Reports and Documents Attached:<br />

None<br />

Date Referred to Board: February 7, 2011<br />

Action Taken: __________________________________________

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!