29.01.2013 Views

02.07.2011 - Village of Deerfield

02.07.2011 - Village of Deerfield

02.07.2011 - Village of Deerfield

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

REQUEST FOR BOARD ACTION<br />

Agenda Item: 11-20<br />

Subject: Approval <strong>of</strong> Wastewater Reclamation Facility Improvement Project Change Order No. 1<br />

Action Requested: Authorize Change Order No. 1 (Electric Service Entrance Allowance) $19,093<br />

Originated By: Director <strong>of</strong> Public Works and Engineering<br />

Referred To: Mayor and Board <strong>of</strong> Trustees<br />

Summary <strong>of</strong> Background and Reason for Request:<br />

The Wastewater Reclamation Facility (WRF) has substantial electrical requirements and is currently served by a large<br />

480 volt transformer. These facilities are on the east side <strong>of</strong> the property and are in conflict with the new aeration tank.<br />

Commonwealth Edison (ComEd) has designed a new transformer and feed for the proposed improvements. Their<br />

preliminary construction cost estimate was $30,000. An allowance for this work was included in the contract<br />

specifications. The ComEd information was refined and updated in mid 2010 with a revised construction cost <strong>of</strong> $43,500.<br />

That revised cost was not reflected in the final contract documents and is the prices for this necessary work that must be<br />

performed by ComEd.<br />

JJ Henderson, ComEd, Strand Associates and <strong>Village</strong> personnel have conducted on site meetings to locate underground<br />

electric facilities and evaluate the actual impacts <strong>of</strong> construction. It has been determined that additional facilities will<br />

need to be moved to protect them from damage. The existing primary conductors to the transformer in the public works<br />

storage yard will be compromised by the over dig for the aeration basin construction. These conductors have to be<br />

relocated or that transformer has to be fed from an alternative direction. The preferred and less expensive alternative is to<br />

re-feed the transformer from the new nearby sectionalizer ($5,593.14) to be installed for the WRF project.<br />

ComEd has submitted their full documentation to the <strong>Village</strong> for review and approval. This includes the Electric<br />

Facilities Service Agreement with an Installation Charge <strong>of</strong> $49,093.14. This includes both the WRF work and the<br />

recently identified storage yard transformer feed. This payment will be made by the contractor after authorization from<br />

the <strong>Village</strong>. The contractor’s allowance for the work was $30,000. We request authorization to increase this allowance<br />

for payment to ComEd by the amount <strong>of</strong> $19,093.14.<br />

Strand Associates has reviewed all the materials and prices submitted and found them to be reasonable and<br />

accurate.<br />

The Director <strong>of</strong> Public Works and Engineering recommends that the Mayor and Board <strong>of</strong> Trustees authorize the increase<br />

in the Electric Service Entrance Allowance, increasing the total contract amount from the base bid <strong>of</strong> $29,450,000 to<br />

$29,469,093.14.<br />

Reports and Documents Attached:<br />

Letter from Strand Recommending Approval <strong>of</strong> Change Order #1<br />

Date Referred to Board: February 7, 2011<br />

Action Taken: __________________________________________

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!