PDF document properties shall include the submittal number for the document<br />

title and the Contractor’s name for the author.<br />

Electronic submittal file sizes shall be limited to 10 MB. When multiple files are<br />

required for a submittal the least number of files possible shall be created.<br />

The contractor shall post submittals and retrieve the District Representative's<br />

submittal review comments through the District Representative's project website<br />

accessible through the Internet. Instruction on procedures for posting and<br />

retrieving submittals will be provided after award of the Contract.<br />

Facsimiles (fax) will not be acceptable. District Representative will not accept<br />

submittals from anyone but Contractor. Submittals shall be consecutively<br />

numbered in direct sequence of submittal and without division by subcontracts or<br />

trades.<br />

1.02. District Representative's Review of Submittals. District Representative's<br />

review of submittals covers only general conformity to the Drawings and<br />

Specifications, external connections, and dimensions that affect the layout; it<br />

does not indicate thorough review of all dimensions, quantities, and details of the<br />

material, equipment, device, or item covered. District Representative's review<br />

shall not relieve Contractor of sole responsibility for errors, omissions, or<br />

deviations in the drawings and data, nor of Contractor's sole responsibility for<br />

compliance with the Contract Documents.<br />

District Representative's submittal review period shall be 21 consecutive<br />

calendar days and shall commence on the first calendar day following receipt of<br />

the submittal or resubmittal in District Representative's office. The time required<br />

to mail the submittal or resubmittal back to Contractor shall not be considered a<br />

part of the submittal review period.<br />

When the drawings and data are returned with review status "NOT<br />

ACCEPTABLE" or "RETURNED FOR CORRECTION", the corrections shall<br />

be made as instructed by District Representative. If submittals are made in hard<br />

copy, five corrected copies shall be resubmitted. If submittals are made<br />

electronically, the corrected drawings and data shall be resubmitted through the<br />

project website. Resubmittals by facsimile or e-mail will not be accepted. When<br />

the drawings and data are returned with review status "EXCEPTIONS NOTED",<br />

"NO EXCEPTIONS NOTED", or "RECORD COPY", no additional copies need<br />

be furnished unless specifically requested by District Representative.<br />

(<strong>CPNMD</strong> )<br />

(INTERCONNECT PIPELINE ) 01300<br />

(167558.0200 ) -3-<br />

(08/01/<strong>12</strong> )