Parts lists and operating and maintenance instructions shall be furnished for<br />

other equipment not listed in the individual equipment sections or the equipment<br />

schedule.<br />

Operation and maintenance manuals shall include the following:<br />

a. Equipment function, normal operating characteristics, and limiting<br />

conditions.<br />

b. Assembly, installation, alignment, adjustment, and checking<br />

instructions.<br />

c. Operating instructions for startup, routine and normal operation,<br />

regulation and control, shutdown, and emergency conditions.<br />

d. Lubrication and maintenance instructions.<br />

e. Guide to troubleshooting.<br />

f. Parts lists and predicted life of parts subject to wear.<br />

g. Outline, cross section, and assembly drawings; District<br />

Representativeing data; and wiring diagrams.<br />

h. Test data and performance curves, where applicable.<br />

The operation and maintenance manuals shall be in addition to any instructions<br />

or parts lists packed with or attached to the equipment when delivered, or which<br />

may be required by Contractor.<br />

Three hard copies of each manual shall be submitted to District Representative<br />

prior to the date of shipment of the equipment. When the O&M manuals are<br />

returned with the review status "RETURNED FOR CORRECTION", the<br />

corrections shall be made as instructed by the District Representative, and two<br />

copies of the corrected portion(s) and one complete corrected copy of the O&M<br />

manual returned to the District Representative. After review by District<br />

Representative, is complete three hard copies of each operation and<br />

maintenance manual shall be prepared and delivered to District Representative<br />

not later than 30 days prior to placing the equipment in operation.<br />

All material shall be marked with project identification, and inapplicable information<br />

shall be marked out or deleted.<br />

Shipment of equipment will not be considered complete until all required manuals<br />

and data have been received.<br />

(<strong>CPNMD</strong> )<br />

(INTERCONNECT PIPELINE ) 01300<br />

(167558.0200 ) -5-<br />

(08/01/<strong>12</strong> )