Section 01320<br />

CONSTRUCTION PROGRESS DOCUMENTATION<br />

1. SCHEDULE OF VALUES. After review of the preliminary schedule at the<br />

preconstruction conference, and before submission of the first Application for<br />

Payment, Contractor shall prepare and submit to District Representative a<br />

Schedule of Values covering each lump sum item. The Schedule of Values,<br />

showing the value of each kind of work, shall be acceptable to District<br />

Representative before any Application for Payment is prepared.<br />

The sum of the items listed in the Schedule of Values shall equal the Contract<br />

Price. Such items as Bond premium, temporary construction facilities, and plant<br />

may be listed separately in the Schedule of Values, provided the amounts can be<br />

substantiated. Overhead and profit shall not be listed as separate items.<br />

The Schedule of Values shall have sufficient detail such that partial completion<br />

of separable items of work can easily be calculated. The Schedule of Values<br />

shall have separate lines for manufacturer's field services, O&M manuals, and<br />

performance testing for each item of equipment requiring such services.<br />

An unbalanced Schedule of Values providing for overpayment of Contractor<br />

on items of Work which would be performed first will not be accepted. The<br />

Schedule of Values shall be revised and resubmitted until acceptable to District<br />

Representative. Final acceptance by District Representative shall indicate only<br />

consent to the Schedule of Values as a basis for preparation of applications for<br />

progress payments, and shall not constitute an agreement as to the value of<br />

each indicated item.<br />

2. SURVEY DATA. All field books, notes, and other data developed by<br />

Contractor in performing surveys required as part of the Work shall be available<br />

to District Representative for examination throughout the construction period. All<br />

such data shall be submitted to District Representative with the other<br />

documentation required for final acceptance of the Work.<br />

3. LAYOUT DATA. Contractor shall keep neat and legible notes of measurements<br />

and calculations made in connection with the layout of the Work. Copies<br />

of such data shall be furnished to the Resident Project Representative for use in<br />

checking Contractor's layout as provided in the Project Requirements section. All<br />

such data considered of value to District will be transmitted to District by District<br />

Representative with other records upon completion of the Work.<br />

End of Section<br />

(<strong>CPNMD</strong> )<br />

(INTERCONNECT PIPELINE ) 01320<br />

(167558.0200 ) -1-<br />

(08/01/<strong>12</strong> )