<strong>Waldner</strong> is investing in production<br />
at the Wangen location<br />
by christine.stiefenhofer@waldner.de<br />
The first construction stage – a new production and<br />
shipping hall for WALDNER Laboreinrichtungen –<br />
will be completed in mid-December.<br />
e are taking an important step in increasing our<br />
"Wcompetitivity and therefore also in safeguarding<br />
the future of the Wangen site", explains Peter Wanner, the<br />
CEO of WALDNER Laboreinrichtungen, with reference to the<br />
total investment of E 10 million. The current building situation<br />
and upcoming investments in machinery made the need<br />
for action increasingly clear.<br />
Peter Wanner (Geschäftsführer<br />
von WALDNER Laboreinrichtungen)<br />
bei der Besichtigung<br />
der baulichen Fortschritte.<br />
Peter Wanner (the CEO of<br />
WALDNER Laboreinrichtungen)<br />
inspecting building progress.<br />
As the concept for the future is designed to be implemented<br />
in stages, the ability to conduct normal business is given at<br />
all times: "The aim of development of the location is on the<br />
one hand to consider the future and on the other to question<br />
the current processing methods. This is not about an<br />
expansion but rather about making the production process<br />
fit for the future! We<br />
will make the whole<br />
company more efficient<br />
and competitive."<br />
Peter Wanner<br />
is convinced of this.<br />
i<br />
i n f o – b o x<br />
Hall size = approx. 7,000 m 2 / approx. 72,000 m 3<br />
Clear hall height = 8 m<br />
Overall hall height = 11.40 m<br />
Die neue Absauganlage hat<br />
frequenzgesteuerte Motoren.<br />
Durch diese passt sich die Anlage<br />
im Verbrauch und in der<br />
Leistung an den Bedarf der<br />
Produktion an.<br />
The new extraction system has<br />
frequency-controlled motors.<br />
These adapt the consumption and<br />
output of the system to production<br />
requirements.<br />
Roof: Flat roof designed as a trapezoidal sheet metal non-insulated roof<br />
Wall: Concrete base with horizontally installed sandwich wall<br />
Floor: 22 cm steel fibre concrete floor with a load of 10 to/m 2<br />
Heating: radiant ceiling panels<br />
Photovoltaik system over whole roof surface with approx. 260 kWpi (kilowatt peak)<br />
The complete hall is equipped with a sprinkler system. The underground sprinkler tank<br />
(water storage tank) has a capacity of approx. 400 m 3 .<br />
Extraction system in the north of the hall with approx. 190,000 m 3 /hr for dust extraction<br />
on the machines.<br />
Internal<br />
33