A 4 Resources<br />
Comparing the resources used for this NSCOGI study with the European Wind Energy<br />
Study (EWIS) study [14], a considerable increase in efficiency of regional cooperation can<br />
be observed:<br />
While the first common TSO-study on Wind Energy (EWIS) used ~4 M€ financed by the EC<br />
plus the same amount own financing, this NSCOGI study built on the existing ENTSO-E’s<br />
Regional Group <strong>North</strong> Sea (RGNS), providing the necessary resources and experience from<br />
recent regional studies. Via this NSCOGI study coming common investigations to be<br />
delivered for the next edition of ENTSO-E’s Ten-Year-Network-Development Plan (TYNDP)<br />
are prepared.<br />
While in EWIS 15 TSOs were involved, the NSCOGI study team comprises 16 TSOs. Both<br />
studies involved 50-60 persons from the different companies delivering part of their time<br />
during the project phase.<br />
While EWIS had a one-year preparatory phase (March 2006 – January 2007) and a three<br />
year project phase (June 2007 – April 2010 = 34 months), this NSCOGI study had half a<br />
year preparatory phase (data gathering) and ~1,5 years of simulating and reporting.<br />
Financing<br />
- by EC<br />
- by TSOs<br />
Resources<br />
- TSOs involved<br />
- persons involved<br />
Time<br />
preparatory phase<br />
simulation/ reporting phase<br />
EWIS NSCOGI<br />
~4 M€<br />
~same amount<br />
15<br />
~60<br />
11 months<br />
34 months<br />
not specified<br />
16<br />
~50<br />
6 months<br />
17 months<br />
Page7-59