INSPECT WIRING AND RECORD ELECTRICAL DATA:<br />

Ratings:<br />

Motor voltage: ________ Motor(s) amps: ________ Oil pump voltage: ________ Starter amps: ________<br />

Line voltages: Motor: _____________ Oil pump: _____________ Controls/oil heater: ____________<br />

Field-installed starters only:<br />

Check continuity T1 to T1, etc (motor to starter power wiring).<br />

Megger starter: Do not megger a motor connected to a solid-state starter, unless the leads to the motor are disconnected and<br />

meggered.<br />

Megger motor Phase to phase Phase to ground<br />

T1-T2 T1-T3 T2-T3 T1-G T2-G T3-G<br />

10-second readings<br />

60-second readings<br />

Polarization ratio<br />

Starter:<br />

Electro-mechanical __________ Electronic __________<br />

Motor load current transformer ratio _____ : _____ Signal resistor size ________ Ohms<br />

Transition timer time __________ seconds<br />

Check magnetic overloads: Add dash pot oil Yes _______ No _______<br />

Solid-state overloadsYes _______ No _______<br />

Solid-state starter: Initial voltage __________ Volts Ramp setting __________ seconds<br />

Controls: safety, operating, etc<br />

Perform controls test Yes _______ No _______<br />

CAUTION: Compressor motor and control centre must be properly and individually connected back to the earth ground in the<br />

starter (in accordance with certified drawings). Yes _______<br />

Run machine:<br />

Do these safeties shut down the machine?<br />

Condenser water flow switch: Yes ________ No ________<br />

Chilled water flow switch: Yes ________ No ________<br />

Pump interlocks: Yes ________ No ________<br />

Initial start:<br />

Line up all valves in accordance with instruction manual: _______ Start water pumps and establish water flow: ________<br />

Oil level and temperature correct: ________ Check oil pump rotation pressure ________<br />

Check compressor motor rotation (motor end sight glass) and record: Clockwise ________<br />

Restart compressor. Bring up to speed. Shut down. Any abnormal coastdown noise?: Yes* ________ No ________<br />

* If yes, determine cause<br />

Start machine and operate. Complete the following:<br />

A. Trim charge and record.<br />

B. Complete any remaining control calibration and record.<br />

C. Take at least 2 sets of operational log readings and record.<br />

D. After machine has been successfully run and set up, shut down and mark shutdown oil and refrigerant levels.<br />

E. Give operating instructions to owner's operating personnel. Hours given: ________ hrs<br />

F. Call your <strong>Carrier</strong> factory representative to report chiller start-up.<br />

Signature: ______________________________________ Date: _________<br />

(<strong>Carrier</strong> technician)<br />

Signature: ______________________________________ Date: _________<br />