19XR (PIC II) Hermetic Centrifugal Liquid Chillers 50 Hz - Carrier
19XR (PIC II) Hermetic Centrifugal Liquid Chillers 50 Hz - Carrier
19XR (PIC II) Hermetic Centrifugal Liquid Chillers 50 Hz - Carrier
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
INSPECT WIRING AND RECORD ELECTRICAL DATA:<br />
Ratings:<br />
Motor voltage: ________ Motor(s) amps: ________ Oil pump voltage: ________ Starter amps: ________<br />
Line voltages: Motor: _____________ Oil pump: _____________ Controls/oil heater: ____________<br />
Field-installed starters only:<br />
Check continuity T1 to T1, etc (motor to starter power wiring).<br />
Megger starter: Do not megger a motor connected to a solid-state starter, unless the leads to the motor are disconnected and<br />
meggered.<br />
Megger motor Phase to phase Phase to ground<br />
T1-T2 T1-T3 T2-T3 T1-G T2-G T3-G<br />
10-second readings<br />
60-second readings<br />
Polarization ratio<br />
Starter:<br />
Electro-mechanical __________ Electronic __________<br />
Motor load current transformer ratio _____ : _____ Signal resistor size ________ Ohms<br />
Transition timer time __________ seconds<br />
Check magnetic overloads: Add dash pot oil Yes _______ No _______<br />
Solid-state overloadsYes _______ No _______<br />
Solid-state starter: Initial voltage __________ Volts Ramp setting __________ seconds<br />
Controls: safety, operating, etc<br />
Perform controls test Yes _______ No _______<br />
CAUTION: Compressor motor and control centre must be properly and individually connected back to the earth ground in the<br />
starter (in accordance with certified drawings). Yes _______<br />
Run machine:<br />
Do these safeties shut down the machine?<br />
Condenser water flow switch: Yes ________ No ________<br />
Chilled water flow switch: Yes ________ No ________<br />
Pump interlocks: Yes ________ No ________<br />
Initial start:<br />
Line up all valves in accordance with instruction manual: _______ Start water pumps and establish water flow: ________<br />
Oil level and temperature correct: ________ Check oil pump rotation pressure ________<br />
Check compressor motor rotation (motor end sight glass) and record: Clockwise ________<br />
Restart compressor. Bring up to speed. Shut down. Any abnormal coastdown noise?: Yes* ________ No ________<br />
* If yes, determine cause<br />
Start machine and operate. Complete the following:<br />
A. Trim charge and record.<br />
B. Complete any remaining control calibration and record.<br />
C. Take at least 2 sets of operational log readings and record.<br />
D. After machine has been successfully run and set up, shut down and mark shutdown oil and refrigerant levels.<br />
E. Give operating instructions to owner's operating personnel. Hours given: ________ hrs<br />
F. Call your <strong>Carrier</strong> factory representative to report chiller start-up.<br />
Signature: ______________________________________ Date: _________<br />
(<strong>Carrier</strong> technician)<br />
Signature: ______________________________________ Date: _________<br />
(Customer representative)<br />
6