03.07.2013 Views

View/Open - Naval Postgraduate School

View/Open - Naval Postgraduate School

View/Open - Naval Postgraduate School

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

nuclear plant construction (Lake, 2002; Kharbanda & Pinto, 1996; Feldman et al., 1988;<br />

Lillington, 2004; Friedrich et al., 1987). Examining construction records from the Nuclear<br />

Regulatory Commission from this period provide two examples of possible tipping point dynamic<br />

failure.<br />

The first example of a project that crossed this tipping point is the Tennessee Valley<br />

Authority’s (TVA) Watts Bar nuclear power plant units 1 and 2. TVA began the construction of<br />

the Watts Bar facility in December of 1972 (NRC, 1982). Originally the facility was to consist of<br />

two 1165 MW units that were to both be on-line by the middle of 1977 (NRC, 1982). However,<br />

as Figure 1 shows, the two units were unable to meet the planned deadline. By mid 1977, Unit 1<br />

was 57% complete and Unit 2 was 49% complete. In May of 1974, the TVA reported delays due<br />

to the redesign of the reactor containment vessel to accommodate higher pressures, an inability<br />

to obtain redesigned anchor bolts and reinforcing rods, and increased time to erect steel plates<br />

that were thicker than the original specifications (NRC, 1982). The work created by the<br />

problems beyond the original scope (e.g., additional anchor bolts or steel plates) are evidence<br />

of adding new tasks. Work was halted in 1980 for five years to address worker safety concerns<br />

with the design of the plant (Lee, 1995). To address these concerns, the TVA spent nearly one<br />

million man hours reviewing the design of the plant (Lee, 1995). This review lead to the<br />

replacement of nearly three million feet of cable, 8,000 pipe supports, and 25,000 conduit<br />

supports (Lee, 1995). The TVA canceled Unit 2 in 1995 with the unit 61% complete (Nuclear<br />

Engineering International, 1995). The TVA estimated that it would cost more than the $1.7<br />

billion already invested in Unit 2 to complete the unit. When Unit 1 finally came on line in 1996,<br />

the TVA had invested nearly $7 billion dollars in the facility (Lillington, 2004). The decrease or<br />

stagnation in the fraction of the total project scope that has been completed (right side of Figure<br />

1) is a characteristic behavior of projects experiencing strong ripple effects.<br />

% Complete<br />

100%<br />

90%<br />

80%<br />

70%<br />

60%<br />

50%<br />

40%<br />

30%<br />

20%<br />

10%<br />

0%<br />

Watts Bar 1<br />

Watts Bar 2<br />

Jul-72 Dec-73 Apr-75 Aug-76 Jan-78 May-79 Oct-80 Feb-82 Jul-83<br />

Figure 1. Watts Bar Construction Progression (1973-1982) (NRC, 1982)<br />

=<br />

=<br />

==================^Åèìáëáíáçå=oÉëÉ~êÅÜW=ÅêÉ~íáåÖ=ëóåÉêÖó=Ñçê=áåÑçêãÉÇ=ÅÜ~åÖÉ=======- 341 -<br />

=<br />

=

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!