ATT 4 – COLLOCATION/AT&T-9STATE<br />
PAGE 23 OF 44<br />
<strong>Southern</strong> <strong>Light</strong><br />
1Q08 GENERIC INTERCONNECTION AGREEMENT – 03/10/08<br />
Additional Structure, as Required)<br />
− 2000 DS0s (Databasing and Installation of Termination Panels, Relay Racks or Additional<br />
Structure, as Required)<br />
− Installation of Cable Racking or Other Support Structure, as Required, to Support CCXCs<br />
(Adequate Floor or Ceiling Structural Capacity Exists and Support/Protection structure for<br />
Fiber Patch Cord is Excluded)<br />
7.1.4.4 Major Augments of physical Collocation Space will be completed within ninety (90) days after<br />
BFFO. All requests for additional Physical Collocation Space (caged or cageless) are included in<br />
this category.<br />
7.1.4.5 Major Augments of virtual Collocation Space will be completed within seventy-five (75) days after<br />
BFFO. This category includes all requests for additional virtual Collocation Space.<br />
7.1.4.6 If <strong>Southern</strong> <strong>Light</strong> submits an Augment that includes two (2) Augment items from the same category<br />
in either Sections 7.1.4.1, 7.1.4.2 or 7.1.4.3 above, the provisioning interval associated with the<br />
next highest Augment category will apply (e.g., if two (2) items from the Minor Augment category<br />
are requested on the same request, then an interval of sixty (60) days from the receipt of the BFFO<br />
would apply, which is the interval associated with the Intermediate Augment category).<br />
7.1.4.7 If <strong>Southern</strong> <strong>Light</strong> submits an Augment that includes three (3) Augment items from the same<br />
category in either Sections 7.1.4.1, 7.1.4.2, or 7.1.4.3 above, the Major Augment interval of ninety<br />
(90) days from the receipt of the BFFO would apply (e.g., if three (3) items from the Simple<br />
Augment category are requested on the same request for a physical Collocation arrangement, then<br />
an interval of ninety (90) days from the receipt of the BFFO would apply, which is the Major<br />
physical Augment interval; likewise if three (3) items from the Simple Augment category are<br />
requested on the same request for a virtual Collocation arrangement, then an interval of seventyfive<br />
(75) days from the receipt of the BFFO would apply, which is the Major virtual Augment<br />
interval).<br />
7.1.4.8 If <strong>Southern</strong> <strong>Light</strong> submits an Augment that includes one (1) Augment item from two (2) separate<br />
categories in Sections 7.1.4.1, 7.1.4.2 and 7.1.4.3 above, the Augment interval associated with the<br />
highest Augment category will apply (e.g., if an item from the Minor Augment category and an item<br />
from the Intermediate Augment category are requested on the same request, then an interval of<br />
sixty (60) days from the receipt of the BFFO would apply, which is the interval associated with the<br />
Intermediate Augment category).<br />
7.1.4.9 All Augments not expressly included in the Simple, Minor, Intermediate or Major Augment<br />
categories, as outlined above, will be placed into the appropriate category as negotiated by<br />
<strong>Southern</strong> <strong>Light</strong> and AT&T. If <strong>Southern</strong> <strong>Light</strong> and AT&T are unable to determine the appropriate<br />
category through negotiation, then the appropriate Major Augment category, identified in Sections<br />
7.1.4.4 and Section 7.1.4.5 above, would apply based on whether the Augment is for <strong>Southern</strong><br />
<strong>Light</strong>’s physical or virtual Collocation Space.<br />
7.1.4.10 Individual application fees associated with Simple, Minor and Intermediate Augments are contained<br />
in Exhibit B. If <strong>Southern</strong> <strong>Light</strong> requests multiple items from different Augment categories, AT&T will<br />
bill <strong>Southern</strong> <strong>Light</strong> the Augment application fee, as identified in Exhibit B, associated with the<br />
higher Augment category only. The appropriate application fee will be assessed to <strong>Southern</strong> <strong>Light</strong><br />
at the time AT&T provides <strong>Southern</strong> <strong>Light</strong> with the Application Response. <strong>Southern</strong> <strong>Light</strong> will be<br />