Key projects for 2008/09<br />
The following specific service improvements and projects have been agreed between the ARC and<br />
<strong>ARTA</strong> through the Long Term Council Community Plan progress. Progress towards the milestones<br />
set out below will be reported to the ARC in each Quarterly <strong>Report</strong>.<br />
Rail Programme of Action<br />
Purchase of electric trains<br />
Construct a large modern station at<br />
Newmarket (to open late <strong>2009</strong>)<br />
Construct a large modern station<br />
at New Lynn (timing dependent<br />
on the ONTRACK double tracking/<br />
under-grounding project)<br />
Construct a new station at the<br />
intersection of Khyber Pass and<br />
Park Road (near <strong>Auckland</strong> Hospital)<br />
Avondale Station upgrade<br />
A trial service from Helensville, for<br />
12 months from July 2008<br />
Four or more trains per hour at<br />
peak times across the current<br />
suburban network from July 2008<br />
Provision of two services per hour<br />
at peak times on the Onehunga<br />
branch line in <strong>2009</strong><br />
Provision of six services per hour at<br />
peak times on the Manukau rail link<br />
A new station serving Parnell and<br />
the Learning Quarter<br />
A new Drury Station<br />
Station upgrades at Baldwin<br />
Avenue, Morningside, Mt Albert,<br />
Remuera, Greenlane, Penrose,<br />
Otahuhu, Te Mahia, Takanini,<br />
Waitakere and Pukekohe<br />
Removed from programme<br />
The Government announced in March <strong>2009</strong> its intention to rescind the<br />
regional fuel tax, and its decision that ownership of any future electric<br />
rolling stock should rest with KiwiRail.<br />
Progressed to schedule<br />
Significant progress has been made on the construction of the new<br />
Newmarket Station over the past year, and the station is due to be opened<br />
in January 2010. Currently, the structure of the station and the link bridge to<br />
Remuera Road have both been completed.<br />
Progressed to schedule<br />
Detailed design has been completed and costs are being finalised, including<br />
cost allocation between <strong>ARTA</strong>, Waitakere City Council and ONTRACK.<br />
Progressed to schedule<br />
The detailed design for the new station, now named Grafton Station, has<br />
been completed and the building consent has been submitted.<br />
Progressed to schedule<br />
Detailed design is due to be completed by August <strong>2009</strong>, and the expectation<br />
is that the station upgrade will be complete in the second quarter of 2010<br />
subject to funding approvals.<br />
Achieved<br />
A trial service from and to Helensville was implemented.<br />
Achieved<br />
This level of service was achieved from 13 July 2008.<br />
Progressed to schedule<br />
<strong>ARTA</strong> has completed planning for the Onehunga Station (ITM site) and is<br />
currently preparing a building consent application for the station.<br />
Progressed to schedule<br />
The location of the Manukau Station has been agreed, and concept design<br />
is progressing. <strong>ARTA</strong> is working with Manukau City Council and KiwiRail to<br />
develop a detailed programme of works subject to NZTA funding.<br />
Progressed to schedule<br />
<strong>ARTA</strong> is working with <strong>Auckland</strong> City Council and KiwiRail to develop<br />
preliminary concepts for a new station.<br />
Removed from programme<br />
<strong>ARTA</strong>’s commitment to construct a Drury station has been reviewed in the<br />
light of KiwiRail’s decision that the southernmost station on the electrified<br />
network will be Papakura.<br />
Partly achieved, programme adjusted<br />
<strong>ARTA</strong> is continuing to work with KiwiRail and the relevant local councils to<br />
finalise the location and scope of works for these stations. Morningside rail<br />
station upgrade was completed during 2008/09.<br />