02.10.2014 Views

ARTA Annual Report 2009 - Auckland Transport

ARTA Annual Report 2009 - Auckland Transport

ARTA Annual Report 2009 - Auckland Transport

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Ferry Programme of Action<br />

Improvements to passenger waiting facilities at Half<br />

Moon Bay<br />

Additional services at Half Moon Bay in 2008<br />

More frequent services to Pine Harbour from mid-2008<br />

More frequent services to West Harbour from 2008 and<br />

Gulf Harbour from <strong>2009</strong><br />

A new ferry wharf and ferry services for Beach Haven<br />

from early <strong>2009</strong><br />

More frequent evening and weekend services to<br />

Devonport from mid-2008<br />

Downtown Ferry Terminal upgrade<br />

Downtown wharf structural renewals<br />

Birkenhead ferry terminal upgrade<br />

Improved facilities at Gulf Harbour<br />

A new ferry terminal at Bayswater, to open early<br />

2010, with more frequent services to Bayswater and<br />

Birkenhead at that time<br />

Achieved<br />

Improvements to passenger waiting facilities were<br />

completed October 2008.<br />

Removed from programme<br />

The costs of additional services to Half Moon Bay have<br />

been investigated further, and they are not considered<br />

to be affordable within current budgets.<br />

Achieved<br />

Additional Pine Harbour services began operating in<br />

March 2008 with an additional vessel and two extra<br />

return journeys each weekday.<br />

Achieved<br />

Additional West Harbour services began in June 2008<br />

with an additional vessel and six extra return journeys<br />

each weekday. An average 10% fare increase was<br />

introduced to offset the increase in subsidy. Patronage<br />

on the Gulf Harbour ferry is low and the service is<br />

under review.<br />

Programme adjusted<br />

A staged option was recommended to construct the<br />

ferry terminal, and provided <strong>ARTA</strong> the option to<br />

minimise the impact on the heritage values of the<br />

existing wharf. Capital funding for the Beach Haven<br />

construction works has been included in the <strong>2009</strong>/10<br />

ARC budget.<br />

Achieved<br />

Additional evening services to Devonport were added<br />

to the Fullers commercial service offering in early 2008<br />

Progressed to schedule<br />

Several improvements to passenger facilities at the<br />

Downtown Ferry Terminal were completed in late 2008,<br />

including:<br />

• Pier 1 glass wall enclosure and ports operations office<br />

• Pier 2 canopy<br />

• Pier 1 to 2 link bridge/promenade extension and<br />

fendering.<br />

Progressed to schedule<br />

An increased scope of work for structural renewals to<br />

the downtown wharf substructures has been agreed,<br />

funding has been approved, and work is progressing as<br />

scheduled, with revised completion due mid-2010.<br />

Progressed to schedule<br />

Concrete repair works commenced in June <strong>2009</strong> with<br />

the intention to install a new hydraulic platform.<br />

The tender package for the project will be completed in<br />

September <strong>2009</strong>, with an estimated project completion<br />

date of January 2010.<br />

Achieved<br />

Improvements to passenger waiting facilities were<br />

completed in October 2008.<br />

Removed from programme<br />

Capital works at Bayswater were deferred to 2012/13<br />

in the ARC Long Term Council Community Plan. Interim<br />

improvements, including parking options and enabling<br />

bus services to terminate closer to the ferry terminal,<br />

are under investigation.<br />

64

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!