Holdings (SHE, Pty Ltd). The main components would be shipped to South Africa<br />

from Germany in containers before being transported to and erected on the site. SHE<br />

will use local contractors to produce the 'feet' of concrete slabs for the units, and to<br />

assist with erection and maintenance of the units and the terrain. SHE will purchase<br />

the property for the duration of the project, estimated at 30-40 years. The property is<br />

currently being used for low-density livestock grazing (sheep, goats, cattle, horses),<br />

typical of such a semi-arid area, and such activities will continue on the property<br />

alongside re-zoning of all or part of the land from agricultural to a different use.<br />

The c. 5,000 ha Portion 3 of the Farm Zuurwater 62 straddles the National N14 Road<br />

about 10 km east of the mining village of Aggeneys, 60 km west of Pofadder and 100<br />

km east of Springbok, in the Khai Ma Local Municipality of the Northern Cape<br />

Province. Most of the farm lies north of the road on flat to undulating terrain classified<br />

as part of the Bushmanland Sandy Grassland vegetation unit (NKb 4), with isolated<br />

mountains that create conditions for the Aggeneys Gravel Vygieveld (SKr 19, Mucina<br />

& Rutherford 2006).<br />

The proposed development is for 26 generation units, with each site capable of<br />

producing 19.5 MWp (megawatts of power), that all together would cover a total area<br />

of about 884 ha (18% of the farm's area) and produce about 500MWp of electricity<br />

daily. Each unit consists of 820 5-solar-panel-deep 'tables', with each table statically<br />

supported on metal legs and beams with the feet anchored on concrete slabs that<br />

rest on the ground surface. Each table is orientated to face due north, at an<br />

appropriate angle (25 o ) to capture as much sunlight as possible throughout the year,<br />

but with a gap between tables of 8.5 m (minimum 7.7 m) to ensure that one table<br />

does not cast shade on another in any of the sun's positions during its annual<br />

passage between the tropical meridians. Each generation unit covers a site of total<br />

area 33,83 ha.<br />

Each solar panel is 1,956 x 992 x 50 mm, can produce 280Wp and weighs 27 kg,<br />

with a total of 1,812,200 panels with a payload mass of almost 50 metric tons<br />

required for the whole development. The panels will be shipped from Germany in<br />

3,596 40' high-cube containers, each with a tare mass of c. 3,800 kg. The concrete<br />

'foot' slabs will be manufactured locally, and possibly the metal frameworks to<br />

support the panels.<br />

SATO Aggeneys July 2011 17