87 Dy. E. E.<br />

ANNEXURE - II<br />

The following additional specification /procedure shall be followed for providing shuttering and centring arrangement for relevant tender<br />

items in various parts <strong>of</strong> this building.<br />

Form <strong>Work</strong>:<br />

In general the formwork should be <strong>of</strong> marine ply woods plates. Only for slab bottom the formwork <strong>of</strong> M.S. plates can be allowed on merit<br />

basis based on the condition <strong>of</strong> M.S. plates if they are suitable designed for the purpose. It will not be binding on the part <strong>of</strong> the Engineer In<br />

charge .to allows for M.S formwork. The thickness <strong>of</strong> marine ply wood with damage surface, varying thickness will not be allowed to be<br />

used. The surface <strong>of</strong> the formwork should be treated properly to prevent adhesion <strong>of</strong> concrete to the forms.<br />

The marine ply wood shuttering plates shall be braced suitable with angle iron or wooding frames to withstand the loads to be<br />

imposed on the formwork and to prevent bending, deflection, deformation in size or displacement <strong>of</strong> the member. The formwork should be<br />

watertight to prevent leakage <strong>of</strong> concrete water or cement slurry from the section.<br />

CENTREING: -<br />

For centering M.S. tubular props and struts with adjustment heights should only be used. The total supporting arrangement shall be<br />

designed by the contractor, confirming the relevant I.S. code and standard practice being adopted in the type <strong>of</strong> work. The Centring<br />

arrangement shall be adequately braced and properly fixed by using appropriate type <strong>of</strong> fastening and fixture to ensure stability and stay <strong>of</strong><br />

the Centring to withstand all loads coming on it. Before commencement <strong>of</strong> this item the total arrangement <strong>of</strong> Centring and work design<br />

Contractor No. <strong>of</strong> correction Executive Engineer