90 Dy. E. E.<br />
ITEM TO INCLUDE:-<br />
i) Cleaning the surface, removing all local material such as debris old treatment coba, I.P.S. flooring etc. and stacking at safe place as<br />
directed.<br />
ii) Preparing surface by removing all debris etc. removing any uneven on local humps etc. sweeping clean etc. complete.<br />
iii) All necessary labour, material, scaffolding, tools and equipment for satisfactory completion <strong>of</strong> the item.<br />
iv) Testing <strong>of</strong> floor by panelling method or any other method as specified.<br />
v) Guarantee for 10 years against any leakages and rectification there<strong>of</strong> within guarantee period.<br />
vi) Cost <strong>of</strong> cement required for grouting as per actual use.<br />
vii) All safety measures such as sign boards red cloth, indications etc. safeguard against any accident or damages to the users.<br />
viii) Curing at least for 10 days.<br />
MODE OF MEASUREMENT :<br />
The contract rate shall be for the actual area treated between edge <strong>of</strong> parapet walls. The separate rate shall be paid for vertical treatment<br />
to parapet on Sq. meter area basis. In case, extra thickness <strong>of</strong> coba is require to be provided to achieve the required gradient, the same shall be<br />
provided only if be directed. The work shall however, be executed as directed above except final finishing <strong>of</strong> the top surface. The rate for<br />
providing extra thickness as above shall be paid per cubic meter for this extra thickness.<br />
GUARANTEE :- The contractor shall submit before starting the work, the guarantee on requisite stamp paper stating that the work shall be completed<br />
satisfactorily and necessary guarantee bond valid for period <strong>of</strong> ten years, effective from date <strong>of</strong> completion <strong>of</strong> work. The guarantee shall clearly<br />
mention that in case there are any leakages due to defective workmanship and poor quality, such defective portion shall be redone following all<br />
above specifications strictly. The rectification work shall be started within stipulated time specified in the notice issued to that effect and<br />
completed as early as possible to the satisfaction and specifications. The decision <strong>of</strong> the Engineer In charge in this respect will be final.<br />
If the contractor fails to carry out the rectification within the time stipulated on the notice the same shall be got executed through other agency at<br />
the risk and cost <strong>of</strong> defaulted contractor as per rules in force.<br />
Contractor No. <strong>of</strong> correction Executive Engineer