<strong>BHEL</strong>-ISG<br />
GENERAL SPECIFICATION FOR<br />
PILING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />
WORKS OF CHP & AHP PACKAGE<br />
2X250 MW BARAUNI THERMAL POWER PROJECT<br />
INSTRUCTION TO BIDDERS<br />
SPECIFICATION NO<br />
IS- 1-10-2013 / 005<br />
DATE: 04/06/2011<br />
VOLUME 1<br />
SECTION 3<br />
successful bidder as per the quoted rate. The above scope is<br />
tentative and subject to change by the <strong>BHEL</strong>.<br />
The location and numbers of structures indicated in plot plan &<br />
related drawings are tentative and are subject to change depending<br />
upon the detail engineering at later date.<br />
The works shall be executed as below:-<br />
1.1 The scope include providing all labour, supervision, material,<br />
scaffolding, construction equipments, tools and plants, temporary<br />
works, supplies including POL, transportation and all incidental<br />
items not shown or specified but reasonably implied or necessary<br />
for the proper completion of work in all respects. Establishment of<br />
laboratory at site with all the required testing facility for concrete,<br />
earthwork, other allied works, preparation of fabrication drawings<br />
etc. are included in the rates for work. Works shall be carried out<br />
based on approved drawings only. The scope of work also includes<br />
providing of PTFE bearing’s design & drawings approval.<br />
1.2 The area of work shall be cleared of all vegetation, rubbish and other<br />
objectionable matter and the materials removed, shall be burnt or<br />
otherwise disposed of as directed by the Engineer-in-charge. No<br />
separate payment shall be made for the above.<br />
1.3 All gold, silver, oil or other minerals of any description and all<br />
precious stones, coins, treasures, relics, antiques, and other similar<br />
things which may be found in or upon the site shall be the property<br />
of <strong>BHEL</strong> / GSECL. The contractor shall duly preserve the same and<br />
from time to time deliver the same to such person or persons as<br />
<strong>BHEL</strong> may from time to time appoint to receive the same.<br />
1.4 All the work areas shall be adequately flood lighted to the<br />
satisfaction of the Engineer-in-Charge when the work is in<br />
progress during the night shifts.<br />
ENQUIRY No.<br />
88/11/6010/AK<br />
REV. R0 PAGE 2 of 8