<strong>BHEL</strong>-ISG<br />
GENERAL SPECIFICATION FOR<br />
PILLING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />
WORKS OF CHP & AHP PACKAGE<br />
2X250 MW BARAUNI THERMAL POWER PROJECT<br />
SPECIAL CONDITIONS OF CONTRACT<br />
SPECIFICATION NO<br />
IS- 1-10-2013 / 005<br />
DATE: 04/06/2011<br />
Volume-1<br />
Section - 6<br />
GENERAL<br />
The special conditions of contract and other contract documents are<br />
complimentary to each other and shall be read in conjunction with<br />
each other. In case of any confliction of meanings between the special<br />
conditions of contract and the <strong>BHEL</strong> GCC, provisions of special<br />
conditions of contract shall over ride the corresponding provisions of<br />
the <strong>BHEL</strong> GCC.<br />
GENERAL SCOPE OF WORK<br />
This tender specification for Pilling, Civil & structural steel works<br />
includes detailed design, engineering, construction , shop & field<br />
fabrication, inspection, storage and inplant transportation for all<br />
facilities of the inplant coal & ash handling system(design & detailing<br />
for AHP will be in <strong>BHEL</strong>/<strong>BHEL</strong> vendor scope) and handing over to<br />
employer as per the scope defined in Section -2, Volume-1.<br />
The detailed scope of work and the technical requirements for the<br />
work to be executed under this specification shall be as per the<br />
approved drawings, technical requirements enclosed in Vol-II<br />
The detail scope of work covered in the section 2 is not a<br />
comprehensive list of items of work involved. The detail scope of work<br />
may vary considerably depending on the actual requirements at site as<br />
per the requirements of the customer if any.<br />
ALSO INCLUDED IN THE SCOPE<br />
Unless otherwise specified, the work to be provided by the contractor<br />
for the items shall include but not be limited to the following:<br />
a) Furnishing all labour, materials, supervision, construction plans,<br />
equipment, supplies, transport to & from the site, fuel, electricity,<br />
compressed air, water, transit and storage insurance and all other<br />
incidental items and temporary works not shown on specified but<br />
ENQUIRY No.<br />
88/11/6010/AK<br />
REV. R0 PAGE 1 of 33