<strong>BHEL</strong>-ISG<br />

GENERAL SPECIFICATION FOR<br />

PILLING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />

WORKS OF CHP & AHP PACKAGE<br />

2X250 MW BARAUNI THERMAL POWER PROJECT<br />

SPECIAL CONDITIONS OF CONTRACT<br />

SPECIFICATION NO<br />

IS- 1-10-2013 / 005<br />

DATE: 04/06/2011<br />

Volume-1<br />

Section - 6<br />

the contract for any materials supplied by the contractor other than<br />

those for which, as stated above, satisfactory proof has already been<br />

furnished, at the cost of the contractor and the contractor shall provide<br />

at his expense all facilities which the engineer may require for the<br />

purpose. If no tests are specified in the contract and such tests are<br />

required by the engineer, the contractor shall provide all facilities<br />

required for the purpose and the charges for these tests shall be borne<br />

by the contractor only.<br />

MATERIAL SUPPLY BY <strong>BHEL</strong> FREE OF COST<br />

The contractor shall at his own expenses provide all construction materials (including<br />

cement) required for the work.<br />

However <strong>BHEL</strong> will supply Structural steel & Reinforcement steel free of cost<br />

as per following terms & conditions:<br />

CHP<br />

All structural & reinforcement steel required for CHP shall be supplied by <strong>BHEL</strong> free<br />

of cost.<br />

AHP<br />

All structural & reinforcement steel required for AHP shall be supplied by <strong>BHEL</strong> free<br />

of cost.<br />

Materials will be issued only for building structures, permanent works<br />

and not for technological ( BAH alone) structures, for making<br />

templates, other temporary works, enabling works etc. and the same<br />

shall not be into account for purpose of material reconciliation.<br />

The contractor shall bear all other costs including the lifting, carting<br />

from issue points to works site/contractor's stores, custody and<br />

handling etc. and return of surplus/serviceable materials to owner's<br />

stores to be designated by the Engineer-in-charge and all expenditure<br />

will be made by the contractor.<br />

The structural steel and reinforcement steel shall be issued in<br />

available lengths / shapes on weight basis and cost of all<br />

straightening, cutting and jointing if any required shall be borne by<br />

ENQUIRY No.<br />