<strong>BHEL</strong>-ISG<br />
GENERAL SPECIFICATION FOR<br />
PILLING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />
WORKS OF CHP & AHP PACKAGE<br />
2X250 MW BARAUNI THERMAL POWER PROJECT<br />
SPECIAL CONDITIONS OF CONTRACT<br />
SPECIFICATION NO<br />
IS- 1-10-2013 / 005<br />
DATE: 04/06/2011<br />
Volume-1<br />
Section - 6<br />
The contractor has to establish / arrange at site the field testing<br />
facilities for ensuring the proper quality, grade and strength of the<br />
materials used in the construction in line with approved field quality<br />
plan / check list. Contractor has to submit detailed report for testing of<br />
all material used etc. All testing shall be done as per IS code<br />
specifications / approved quality plan. If further test is required by the<br />
engineer to be carried from outside laboratory, the cost of the same<br />
shall be borne by the contractor.<br />
COMPLETION OF WORK<br />
The works shall be completed to the entire satisfaction of the engineer<br />
and in accordance with the completion schedule as specified in the<br />
contract and all unused stores and materials, tools, plant, equipment,<br />
temporary buildings, site office, labour hutments and other things shall<br />
be removed and the site and work cleared of rubbish and all waste<br />
materials and delivered up clean and tidy to the satisfaction of the<br />
engineer at the contractor's expenses.<br />
<strong>BHEL</strong> shall have power to take over from the contractor from time to<br />
time such sections of the work as have been completed to the<br />
satisfaction of the engineer. Such work however shall not be treated as<br />
have been completed until the extra works are executed to the<br />
satisfaction of engineer. The guarantee period shall commence only<br />
after handing over of the entire works.<br />
The engineer shall certify to the contractor the date on which the work<br />
is completed and the date thereof.<br />
RECORDS AND MEASUREMENT<br />
All items having a financial value shall be entered in <strong>BHEL</strong><br />
measurement book so that a complete record is obtained of all works<br />
performed under the contract.<br />
ITEM RATE omissions will be entered for deduction. Measurement shall<br />
ENQUIRY No.<br />
88/11/6010/AK<br />
REV. R0 PAGE 23 of 33