<strong>BHEL</strong>-ISG<br />

GENERAL SPECIFICATION FOR<br />

PILLING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />

WORKS OF CHP & AHP PACKAGE<br />

2X250 MW BARAUNI THERMAL POWER PROJECT<br />

SPECIAL CONDITIONS OF CONTRACT<br />

SPECIFICATION NO<br />

IS- 1-10-2013 / 005<br />

DATE: 04/06/2011<br />

Volume-1<br />

Section - 6<br />

The contractor has to establish / arrange at site the field testing<br />

facilities for ensuring the proper quality, grade and strength of the<br />

materials used in the construction in line with approved field quality<br />

plan / check list. Contractor has to submit detailed report for testing of<br />

all material used etc. All testing shall be done as per IS code<br />

specifications / approved quality plan. If further test is required by the<br />

engineer to be carried from outside laboratory, the cost of the same<br />

shall be borne by the contractor.<br />

COMPLETION OF WORK<br />

The works shall be completed to the entire satisfaction of the engineer<br />

and in accordance with the completion schedule as specified in the<br />

contract and all unused stores and materials, tools, plant, equipment,<br />

temporary buildings, site office, labour hutments and other things shall<br />

be removed and the site and work cleared of rubbish and all waste<br />

materials and delivered up clean and tidy to the satisfaction of the<br />

engineer at the contractor's expenses.<br />

<strong>BHEL</strong> shall have power to take over from the contractor from time to<br />

time such sections of the work as have been completed to the<br />

satisfaction of the engineer. Such work however shall not be treated as<br />

have been completed until the extra works are executed to the<br />

satisfaction of engineer. The guarantee period shall commence only<br />

after handing over of the entire works.<br />

The engineer shall certify to the contractor the date on which the work<br />

is completed and the date thereof.<br />

RECORDS AND MEASUREMENT<br />

All items having a financial value shall be entered in <strong>BHEL</strong><br />

measurement book so that a complete record is obtained of all works<br />

performed under the contract.<br />

ITEM RATE omissions will be entered for deduction. Measurement shall<br />

ENQUIRY No.<br />

88/11/6010/AK<br />

REV. R0 PAGE 23 of 33