<strong>BHEL</strong>-ISG<br />

GENERAL SPECIFICATION FOR<br />

PILLING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />

WORKS OF CHP & AHP PACKAGE<br />

2X250 MW BARAUNI THERMAL POWER PROJECT<br />

SPECIAL CONDITIONS OF CONTRACT<br />

SPECIFICATION NO<br />

IS- 1-10-2013 / 005<br />

DATE: 04/06/2011<br />

Volume-1<br />

Section - 6<br />

The contractor, in the event of this work awarded to him, shall<br />

establish an office at site and keep posted an authorized, responsible<br />

officer with valid Power of Attorney for the purpose of the contract.<br />

Any order or instructions of the engineer or his duly authorized<br />

representative, communicated to the contractor's representative at<br />

site office will be deemed to have been communicated to the<br />

contractor at his legal address.<br />

SITE FACILITIES<br />

LAND<br />

<strong>BHEL</strong> shall allot land to the contractor if customer GSECL allots the<br />

same to <strong>BHEL</strong> for his office & stores. Contractor must maintain the<br />

areas allotted to him in a neat and clean condition as required by the<br />

Employer. The contractor shall provide adequate storage, testing and<br />

office facilities with approval from the engineer. The rate quoted by<br />

the contractor shall be deemed to include for these and no separate<br />

payment will be made towards these.<br />

On completion of work, the site shall be cleaned by the contactor of all<br />

materials, temporary sheds, debris, rubbish plants and equipments,<br />

belonging to the contractor at no extra cost. The site and surroundings<br />

shall be handed over in neat and clean conditions. Periodical house<br />

keeping shall be done by contractor as per the instructions of <strong>BHEL</strong><br />

and GSECL at no extra cost. In case of any failure by the contractor,<br />

the employer will get set at risk and cost of the contractor.<br />

SUPPLY OF POWER, WATER, ETC.<br />

Construction power and construction water shall be supplied free of cost.<br />

However this shall not be binding on <strong>BHEL</strong> / Customer. In case <strong>BHEL</strong> /<br />

Customer are unable to supply due to any reasons, contractor shall<br />

arrange Construction power and construction water on his own.<br />

However both construction power & water is supplied at one point within<br />

the thermal power plant boundary. Successful contractor of <strong>BHEL</strong> shall<br />

arrange by suitable means to tap the same. All the safety precautions shall<br />

ENQUIRY No.<br />

88/11/6010/AK<br />

REV. R0 PAGE 4 of 33

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!