<strong>BHEL</strong>-ISG<br />

GENERAL SPECIFICATION FOR<br />

PILING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />

WORKS OF CHP & AHP PACKAGE<br />

2X250 MW BARAUNI THERMAL POWER PROJECT<br />

PROJECT COMPLETION SCHEDULE<br />

SPECIFICATION NO<br />

IS- 1-10-2013 / 005<br />

DATE: 04/06/2011<br />

VOLUME 1/<br />

SECTION 4<br />

all his temporary structures for stores, office sheds and labour colony hutments etc and<br />

clear the debris and handover the area in original good condition.<br />

1.05 The total completion period is 24 months from the date of LOI. However<br />

stage wise fronts for the erection of equipments have to be handed over to the<br />

other executing agencies of the project.<br />

ENQUIRY No.<br />

88/11/6010/AK<br />

REV. R0 PAGE 2 of 2