<strong>BHEL</strong>-ISG<br />
GENERAL SPECIFICATION FOR<br />
PILING, CIVIL, STRUCTURAL & ARCHITECTURAL<br />
WORKS OF CHP & AHP PACKAGE<br />
2X250 MW BARAUNI THERMAL POWER PROJECT<br />
PROJECT COMPLETION SCHEDULE<br />
SPECIFICATION NO<br />
IS- 1-10-2013 / 005<br />
DATE: 04/06/2011<br />
VOLUME 1/<br />
SECTION 4<br />
all his temporary structures for stores, office sheds and labour colony hutments etc and<br />
clear the debris and handover the area in original good condition.<br />
1.05 The total completion period is 24 months from the date of LOI. However<br />
stage wise fronts for the erection of equipments have to be handed over to the<br />
other executing agencies of the project.<br />