Transitway Conversion<br />
• Conversion of the Transitway<br />
– In open areas, ballast and track will be installed on top of the<br />
existing roadway<br />
– Track through the stations will be directly fixed to a concrete<br />
slab for ease of maintenance<br />
– Minor changes to drainage will be required<br />
– Some structures will require modifications to increase vertical<br />
clearances<br />
• Once a section is converted it is unlikely that buses (or<br />
other vehicles) will operate along that section<br />
Construction Staging<br />
• Staging g will be determined by the successful contractors,<br />
but will follow these principles:<br />
– The tunnel and underground stations will likely start first, as<br />
these elements take the longest to construct<br />
– The Maintenance and Storage Facility must be completed<br />
midway through the construction of the project to allow for<br />
vehicle delivery and testing<br />
– Major work at Bayview, Hurdman and Blair is off the existing<br />
Transitway and can be done with minimal disruption to bus<br />
service<br />
– Conversion of the Transitway will be done in logical segments to<br />
maintain bus service on the Transitway for as long as possible<br />
Construction Staging<br />
• The project will be staged to:<br />
– Minimize construction cost,<br />
– Minimize traffic and bus service disruption,<br />
– Optimize cash flow, and<br />
– Maximize contractor efficiency<br />
• Once construction starts in an area, bus service will be<br />
rerouted<br />
• After construction is complete there will be a 6-8 month<br />
period for station fit-out, testing and commissioning<br />
before revenue service starts<br />
Rail Operations<br />
• Track, ,power and systems installation at the<br />
Maintenance and Storage Facility will be completed<br />
before the vehicles arrive<br />
• Testing in the yard and sections of the line close to the<br />
Maintenance and Storage Facility will begin as soon as<br />
possible<br />
• Each section of track that is completed will require a<br />
testing and commissioning period<br />
• Crossovers will be provided d at the terminus stations ti and<br />
at key points along the line to allow trains to reverse<br />
direction