Downtown <strong>Ottawa</strong> Transit Tunnel:<br />
Tunney’s Pasture to Blair Station via a Downtown LRT<br />
Tunnel<br />
Planning and Environmental<br />
Assessment Study<br />
Consultation Group Meeting #6<br />
Presentation<br />
17 February 2010<br />
Meeting Agenda<br />
• Introduction: Study Team, Consultation Group members<br />
• DOTT project update<br />
• EA process<br />
– Environmental effects and mitigation<br />
– Project benefits<br />
– Assessment of effects<br />
– Commitments to future work<br />
• Schedule update/process moving forward<br />
DOTT Project Update<br />
• Transit Technology Choice approved by Council on 25<br />
November 2009<br />
• Recommended Plan (functional design) approved by<br />
Council on 13 January 2010<br />
• EA Notice of Commencement posted on 12 February<br />
2010<br />
• Public Open House for EA phase on 23 February 2010<br />
Overview of Recommended Plan<br />
• Council approved functional design for project<br />
components, including:<br />
– LRT alignment<br />
– Station locations and designs<br />
– Maintenance and Storage Facility