<strong>Condit</strong> <strong>Dam</strong> Hydroelectric Project<br />
Final Supplemental EIS<br />
addition, the County lists the lower White Salmon River as a shoreline of state-wide<br />
significance. Shorelines of state-wide significance are recognized as deserving consideration<br />
beyond that prescribed to other bodies.<br />
Wetlands, rivers, buffers, fish and wildlife habitat conservation areas, and geologically<br />
hazardous, seismic and landslide hazards are all discussed in more detail in other sections.<br />
Volcanic and mine hazard areas are outside the proposed action area.<br />
There are no aquifer recharge areas mapped in Klickitat or Skamania Counties in the<br />
proposed action area. However, as part of the Shoreline Master Programs, various activities<br />
may be reviewed to determine potential effects and may require permits on a case-by-case<br />
basis. Although frequently flooded areas are not currently present in most of the project area<br />
because of the dam and canyon, floodplains are present. Various activities may be reviewed<br />
on a case-by-case basis.<br />
4.9.2 Impacts<br />
Pre-<strong>Dam</strong> <strong>Removal</strong> and <strong>Dam</strong> Breaching and <strong>Removal</strong><br />
Land Use<br />
The proposed action would affect land uses along or near the former shoreline both during<br />
and after construction. During construction, sites along or near the reservoir would be used<br />
for work areas, construction staging, or for disposal. In addition, access roads would be built<br />
in several locations.<br />
Work areas identified include one around the dam site for dam removal; one along the<br />
flowline for its removal; one near the powerhouse to remove the penstock; one near the surge<br />
tank for tank removal; one near the tail race to place fill in the area; one near the substation<br />
for substation removal and one along the powerline for powerline removal; one near the Big<br />
White Fish Ponds to clean the ponds; one near Northwestern Lake Bridge for bridge<br />
modifications; one along Northwestern Lake for sediment stabilization, woody debris<br />
management, and boat dock and cofferdam removals; and one along the shoreline about 1<br />
mile above the dam to reestablish a water line below the sediment level. Work areas are<br />
shown on Figures 3-1 through 3-6 in Chapter 3.<br />
Staging areas identified include one adjacent to Powerhouse Road near the dam; one near the<br />
Powerhouse Road bend; one in the upland area off of Powerhouse Road for staging and<br />
stockpiling; one near the flowline; and one at the Becker site for flowline materials and dam<br />
removal equipment. Staging areas and associated access roads are shown on Figures 3-1<br />
through 3-6 in Chapter 3.<br />
In the upland staging area, about 7 acres would be located on PacifiCorp’s land near Well<br />
No. 2 (City of White Salmon) and near proposed Klickitat County plats (near Tamarack<br />
Road).<br />
Potential impacts to the well relate to a well setback area (aquifer recharge and protection)<br />
and to County subdivision procedures. In addition, a portion of this area (about 2 acres) may<br />
be used for concrete storage or disposal.<br />
4.9-3