13.07.2015 Views

Warrawee Substation - Review of Environmental Factors

Warrawee Substation - Review of Environmental Factors

Warrawee Substation - Review of Environmental Factors

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Assessment <strong>of</strong> the environmental impacts and risksIssueNoise andvibrationControl measuresminimises windblown or traffic generated dust. Areas that maybe inaccessible by water carts would be kept in a condition thatminimises windblown or traffic generated dust using othermeans.All trucks would be covered when transporting material to andfrom the site.All construction plant and machinery would be fitted withemission control devices complying with Australian DesignStandards.Plan works to start at 7am such to avoid the need to complywith night time criteria and sleep disturbance criteria.Noise emission levels <strong>of</strong> all critical items <strong>of</strong> mobile plant andequipment should be checked for compliance with noise limitsappropriate to those items prior to the equipment going intoregular service. To this end, a testing regime should beestablished with the principal contractor using manufacturerdata where possible.All fixed plant and stationary mobile plant at the work sitesshould be appropriately selected, and where feasible, fittedwith silencers, acoustical enclosures and other noiseattenuation measures.Erection <strong>of</strong> a 2.4 metre high plywood noise barrier around thesite (including compound) to attenuate levels <strong>of</strong> constructionshould be considered during construction planning, as thiswould potentially contribute up to a 10dB attenuation <strong>of</strong> noiselevels at receiver. However, due to the topography <strong>of</strong> the site,use <strong>of</strong> noise barriers on site may only provide limited benefit.Limit usage <strong>of</strong> hydraulic hammers whenever possible andinstead use rock saws and rippers; or if necessary utilise quiet‘city hammers’ as appropriate.Ensure that truck movements along the work site areperformed in an efficient manner to minimise the need forreversing, therefore minimising reversing alarm noise, anduse smart reversing alarms or squawkers in place <strong>of</strong>traditional reversing alarms for all mobile plant to minimise theintrusiveness <strong>of</strong> reversing alarms.Conduct a combination <strong>of</strong> attended and unattended noisemonitoring <strong>of</strong> works during the initial stages especially ‘Out-Of-Hours’ works at the closest receivers to record typicallevels at the residential receivers.Communicate with the impacted residents by clearlyexplaining the duration, nature <strong>of</strong> works prior to and during<strong>Warrawee</strong> <strong>Substation</strong> Project/<strong>Review</strong> <strong>of</strong> <strong>Environmental</strong> <strong>Factors</strong>Page 56 <strong>of</strong> 64

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!