54 EXCEEDING EXPECTATIONSWBI’s turnkey scope-of-work for the National Gypsum multi-million dollar industrialmanufacturing facility in Mount Holly, North Carolina included all layout, excavation,stone base, foundations, pits, piers, columns, walls, trenches, and slab-on-grade concreteconstruction work associated with the new major wallboard manufacturing facility
It was crucial that the concrete work remain on schedule, as the drywall and othersubcontractors were following closely behind the Wayne Brothers crews, trying to maintaintheir own schedules. WBI used a RCS Self-Climbing System to supplement the busy towercrane on site, as well as a central concrete pump, two Putzmeister booms and three towers. Inorder to use the tower crane more efficiently, the Wayne Brothers crews were divided, allowingthe “vertical crew” to begin work at 4 a.m., and the other crew to hold a safety briefing, thenbegin using the crane at 8 a.m.In addition to placing 460,000 square feet of slab formwork on the Ashton site, WayneBrothers was responsible for placing 1,500 tons of reinforcing steel and 500,000 pounds ofpost-tension cables. Self Consolidating Concrete (SCC) was used on the project to providemore durable, curl-resistant and stronger floors.Even before work on Ashton Southend concluded in September 2008, Wayne Brothersgrading crews were preparing the Charlotte site on which the Premier Medical Office Buildingwas to be erected. General Contractor Bovis Lend Lease awarded contracts to WBI for boththe site work and concrete operations on the office building. The ability of Wayne Brothersto coordinate the civil, infrastructure and concrete divisions resulted in substantial timesavings. The Civil and Infrastructure division began work in June 2008 on the site, clearingand grubbing 12 acres, performing the site cut and fill, blasting rock, and exporting unsuitablematerials and importing suitable fill. They also made a 36” bore under an existing road thatremained in operation, installed a RCP storm drain, relocated utilities, created three turnlanes and a median relocation, and made the necessary signaling changes arising from theintersection changes. Because WBI was able to sequence its activities to allow footings tobegin more quickly, the concrete group began its work six weeks ahead of schedule, reducingthe company’s time on the site and allowing other sub-contractors to begin work on theirphases earlier than scheduled, supporting the overall project schedule.Because WBI was contracted for all the exterior concrete, including curb and gutter andconcrete paving, the risks that concrete contracts would overlap or that some item wouldnot be covered at all, were minimized. WBI surveyors worked closely with the site engineer topredict, avoid, and lessen any potential drainage issues.In August 2009, Wayne Brothers planners were gratified when they were enabled tocomplete the company’s portion of the Premier Medical Office Building located in Charlotteahead of schedule, while maintaining the highest quality and exceeding contract specifications.A New55
- Page 3 and 4:
BY CLARENCE HORTONTHE STORY OF WAYN
- Page 5 and 6:
Four GenerationsPictured left to ri
- Page 7:
with growth, new buildings, expansi
- Page 10 and 11:
Lancaster Valley of Pennsylvania an
- Page 12 and 13: long period of illness. She had liv
- Page 14 and 15: Claude Delmar WayneBorn February 20
- Page 16 and 17: The Jesse Everett Wayne family circ
- Page 19 and 20: PiedmontCHAPTER TWOThe first major
- Page 21 and 22: Keith and Eric as young boyson the
- Page 23 and 24: When work was slow at the sawmill,
- Page 25 and 26: Bobby Phillips,Eric Wayne andKeith
- Page 27 and 28: The Waynes were fortunate to be abl
- Page 29: 350,000 sf warehouse in Rock Hill S
- Page 32 and 33: those submitted by more experienced
- Page 34 and 35: emodeled into a modern office facil
- Page 36 and 37: elieves that a recognition of chang
- Page 38 and 39: Walnut Creek Amphitheater in Raleig
- Page 40 and 41: skill level and English proficiency
- Page 42 and 43: successful both for WBI and the new
- Page 44 and 45: flatter and more level floor surfac
- Page 46 and 47: In August 1996, Isaiah Wayne, oldes
- Page 48 and 49: 40 EXCEEDING EXPECTATIONS
- Page 50 and 51: Wayne graduated from high school in
- Page 52 and 53: When interviewed for an article in
- Page 54 and 55: Executive Management Training Progr
- Page 56 and 57: employees, Matthew Surface and Milt
- Page 58 and 59: Ashton Southend Apartments located
- Page 60 and 61: NASCAR racing community and automob
- Page 64 and 65: As work on the Premier MOB site was
- Page 67 and 68: A TurningCHAPTER FIVEAfter more tha
- Page 69 and 70: McLeod Hospital - ICU Tower100’ d
- Page 71 and 72: fast tracked project. His impressio
- Page 73 and 74: BB&T Ballpark Home Suite ShoredSlab
- Page 75 and 76: the day “when 80% of the issues t
- Page 77 and 78: Joaquin Reveles was recognized for
- Page 79 and 80: Wayne Brothers provideda turnkey si
- Page 81 and 82: equired tolerances were exacting. T
- Page 83 and 84: Building on theCHAPTER SIXFor Shann
- Page 85 and 86: WBI’s Civil andConcrete Groupswer
- Page 87 and 88: the Winston-Salem Caterpillar plant
- Page 89 and 90: project for DPR/Fortis, a first-tim
- Page 91 and 92: Talison Row Apartments inDaniel Isl
- Page 93 and 94: Jason Sisk describes the emphasis o
- Page 95: Training on theLaser ScreedTraining
- Page 98 and 99: years.” While Mr. Ashworth agrees
- Page 100 and 101: Chad HensleyVP and Project Executiv
- Page 102 and 103: Cancer Center, the company carried
- Page 104 and 105: Cherie Berry presentedthe ABC’s G
- Page 106 and 107: Gary Akers and his team of WBI carp
- Page 108 and 109: WBI’s BB&T Ballpark crew celebrat
- Page 110 and 111: Jim ElderSenior EstimatorJim Elder
- Page 113 and 114:
The NextCHAPTER EIGHTAlthough Wayne
- Page 115 and 116:
Reveal of theproposed designfor WBI
- Page 117 and 118:
three county area, “coming togeth
- Page 119 and 120:
Curb and sidewalk construction atth
- Page 121 and 122:
is also room in the large, easily-a
- Page 123 and 124:
In announcing the addition of Isaia
- Page 125 and 126:
Peterbuilt Dump Truck /Interstate T
- Page 127 and 128:
Terrie Simone, Lacie Jones, Casey F
- Page 129 and 130:
craftsmanship; a vision for the fut
- Page 132:
“Since its founding in 1985 as a