SECTION 5.0 CONSTRUCTION MANAGEMENT PROCEDURES<br />

5.2 Contract Document Control<br />

The Project Construction Manager will obtain two complete copies of the executed Contract,<br />

with full size drawings to be used as the official onsite Contract. A copy will also be<br />

maintained by the Design Engineer. One copy will be stored for reference while the other<br />

will be used extensively by site staff and marked up with changes and references to<br />

submittals, RFI’s, Field Work Directives, and Change Orders.<br />

5.2.1 Changes to Contract Documents<br />

The Project Construction Manager or Field Inspector will post changes to the official onsite<br />

Contract Documents after incorporation of the change in the Contract by Field Work<br />

Directive or Change Order. The Project Construction Manager will distribute copies of the<br />

executed contract changes in accordance with Table 5-1 and Figure 5-1.<br />

TABLE 5-1<br />

Distribution of Contract Change Documentation<br />

Proponent<br />

Field Work Directive<br />

or Change Order<br />

Specifications<br />

Full-Size<br />

Drawings<br />

Design Engineer* 1 copy 1 copy 1 copy<br />

Project Construction Manager 1 copy 1 copy 1 copy<br />

C-P/DPW Chief Construction Engineer* 1 copy 1 copy 1 copy<br />

Program Construction Manager* 1 copy 1 copy 1 copy<br />

* When state, county, or city coordination is involved, sufficient copies will be provided for distribution to<br />

those agencies.<br />

Drawings or specifications superseded by subsequent contract changes will be retained for<br />

record purposes and marked “superseded” (SS), date superseded, and Field Work Directive<br />

or Change Order number associated with change.<br />

5.2.2 Contract Document Revision Log<br />

The Project Construction Manager will maintain and distribute a log of specifications and<br />

drawings that shows the latest current revision and which revisions have been superseded<br />

since contract award.<br />

5.2.3 Record Drawings<br />

Record Drawings are required to provide information as indicated by the Contract<br />

Documents. The Record Drawings include pertinent information from shop drawings and<br />

submittals, as well as any changes from the original drawing. During construction, it is the<br />

primary responsibility of the Contractor and the secondary responsibility of the Field<br />

Inspector under the direction of the Project Construction Manager to ensure Record<br />

Drawings are kept current. As a minimum, Record Drawings will contain the following:<br />

<br />

Revisions, additions, or deletions; accompanied by sufficient annotations to adequately<br />

describe the as-built condition.<br />

GNV310133632155.DOC/090840001 5-5