Contents
Construction Management Plan - Baton Rouge Department of Public ...
Construction Management Plan - Baton Rouge Department of Public ...
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
SECTION 5.0 CONSTRUCTION MANAGEMENT PROCEDURES<br />
5.3.2 Transmittal Forms<br />
The Contractor must use a C-P/DPW Form 005 “Transmittal of Contractor’s Submittal” for<br />
submittals, shop drawings, and samples. Standard C-P/DPW forms will also be used along<br />
with other forms listed herein, and as required by the Contract Documents. Approvals<br />
required by a public agency will be obtained by the Contractor prior to the submittal to the<br />
Project Construction Manager. Evidence of such approval will accompany the transmittal.<br />
5.3.3 Submittal Schedule and Review Procedures<br />
The Contractor is required to include submittal requirements in the project schedule. The<br />
submission schedule will be reviewed by the Project Construction Manager, field staff, and<br />
Design Engineer to ensure timely submissions are identified for items required by the<br />
specifications, that submissions are in sequence with the construction schedule, and that<br />
sufficient time is allowed for review and response. The Project Construction Manager and<br />
Field Inspectors are expected to inform the Contractor when the submission schedule is not<br />
being met. A description of the submittal process is presented below.<br />
Transmittal of Submittal: The Contractor will upload submittals to the Prolog website.<br />
Each submittal shall be accompanied by a Transmittal of Contractor’s Submittal with the<br />
appropriate submittal number as defined in the Contract Documents and reference to<br />
relevant drawing and/or specification section. The Contractor will include a statement that<br />
they have reviewed the submittal materials, including those coming from subcontractors,<br />
and have verified that to the best of their understanding they fully meet the contract<br />
requirements. If there are exceptions to the drawings or specifications, they will be stated on<br />
the Transmittal of Contractor’s Submittal.<br />
Design Engineer or C-P/DPW Review: Submittal reviews are required to determine<br />
adequacy, completeness, and compliance with Contract Documents. Should Design<br />
Engineer determine submittal is incomplete, they will immediately return unreviewed with<br />
specific comments to Contractor. Exceptions to review of incomplete submittals, may be<br />
allowed if Design Engineer is notified before submission and agrees to review partial<br />
submittal.<br />
The Project Construction Manager will deliver the copy to C-P/DPW staff if requested. The<br />
C-P/DPW review time is anticipated to be 5 working days. C-P/DPW comments shall be<br />
transmitted to Project Construction Manager who will in turn transmit to Design Engineer.<br />
The Design Engineer will consider the C-P/DPW review comments in with their comments<br />
before returning submittal to Contractor.<br />
5.4 Clarifications<br />
Each construction project expects that additional information will be required throughout<br />
duration of project. Information will be provided by the Design Engineer as required, and<br />
when requested by the Field Inspector, Project Construction Manager, or the Contractor.<br />
5.4.1 Request for Information (RFI)<br />
RFIs will be initiated by Contractor via the Prolog website. RFIs will be submitted using the<br />
Prolog website Request for Information form transmitted electronically (see Figure 5-3).<br />
GNV310133632155.DOC/090840001 5-9