SECTION 10.0<br />
Substantial Completion and Final Inspection<br />
10.1 General<br />
The Contractor will notify the CH2M HILL Project Construction Manager when elements of<br />
the project are substantially completed. The CH2M HILL Project Construction Manager will<br />
arrange for inspection of the work, which, as a minimum, will consist of at least a<br />
substantial completion inspection and a final inspection. C-P/DPW may assume beneficial<br />
occupancy at any time following the successful substantial completion inspection. Beneficial<br />
occupancy infers that the element of work and/or the facility is operational as intended and<br />
that C-P/DPW assumes responsibility for operating and maintaining a facility with an<br />
agreed list of minor contractor actions remaining.<br />
10.2 Substantial Completion Inspection<br />
10.2.1 Substantial Completion Date<br />
The date of substantial completion is determined by the CH2M HILL Project Construction<br />
Manager in accordance with the Contract Documents.<br />
10.2.2 Inspection Participants<br />
Substantial completion inspections will be arranged by the CH2M HILL Project<br />
Construction Manager based on notification by the Contractor that the work is substantially<br />
complete. Mandatory participants include:<br />
C-P/DPW Chief Construction Engineer<br />
Project Construction Manager<br />
Program Construction Manager<br />
Field Inspectors<br />
C-P/DPW Owning Department Representative (i.e., from Treatment )<br />
Contractor<br />
Design Engineer(s)<br />
Outside agencies, as required<br />
The Contractor or the CH2M HILL Project Construction Manager may call for assistance<br />
from specialists in conducting the substantial completion inspection, depending on the<br />
complexity of the work.<br />
10.2.3 Substantial Completion Inspection Guidelines<br />
The substantial completion inspection will be structured to ensure that:<br />
The work has been completed in substantial conformance with the Contract in<br />
preparation for a final inspection.<br />
<br />
Installed equipment works properly.<br />
GNV310133632155.DOC/090840001 10-1