SECTION 10.0<br />

Substantial Completion and Final Inspection<br />

10.1 General<br />

The Contractor will notify the CH2M HILL Project Construction Manager when elements of<br />

the project are substantially completed. The CH2M HILL Project Construction Manager will<br />

arrange for inspection of the work, which, as a minimum, will consist of at least a<br />

substantial completion inspection and a final inspection. C-P/DPW may assume beneficial<br />

occupancy at any time following the successful substantial completion inspection. Beneficial<br />

occupancy infers that the element of work and/or the facility is operational as intended and<br />

that C-P/DPW assumes responsibility for operating and maintaining a facility with an<br />

agreed list of minor contractor actions remaining.<br />

10.2 Substantial Completion Inspection<br />

10.2.1 Substantial Completion Date<br />

The date of substantial completion is determined by the CH2M HILL Project Construction<br />

Manager in accordance with the Contract Documents.<br />

10.2.2 Inspection Participants<br />

Substantial completion inspections will be arranged by the CH2M HILL Project<br />

Construction Manager based on notification by the Contractor that the work is substantially<br />

complete. Mandatory participants include:<br />

C-P/DPW Chief Construction Engineer<br />

Project Construction Manager<br />

Program Construction Manager<br />

Field Inspectors<br />

C-P/DPW Owning Department Representative (i.e., from Treatment )<br />

Contractor<br />

Design Engineer(s)<br />

Outside agencies, as required<br />

The Contractor or the CH2M HILL Project Construction Manager may call for assistance<br />

from specialists in conducting the substantial completion inspection, depending on the<br />

complexity of the work.<br />

10.2.3 Substantial Completion Inspection Guidelines<br />

The substantial completion inspection will be structured to ensure that:<br />

The work has been completed in substantial conformance with the Contract in<br />

preparation for a final inspection.<br />

<br />

Installed equipment works properly.<br />