27.08.2015 Views

Contents

Construction Management Plan - Baton Rouge Department of Public ...

Construction Management Plan - Baton Rouge Department of Public ...

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SECTION 8<br />

Inspections and QA/QC Testing<br />

8.1 General<br />

This section establishes procedures for inspection of work in progress either at the site or off<br />

site. Inspection includes those actions that demonstrate and document compliance by the<br />

Contractor to predetermined quality requirements as defined by the Contract Documents.<br />

Inspection can be categorized into three levels.<br />

<br />

<br />

<br />

First level inspection initially performed by Contractor, frequently confirmed by Field<br />

Inspector, performed during each work activity to ensure Contractor’s activities create<br />

an end product that meets contractual requirements.<br />

Second level inspection includes audit activities by the Project Construction Manager<br />

which ensure first level inspection activities are occurring and are effective.<br />

Third level inspection occurs at the acceptance stage to verify work does in fact meet the<br />

physical and functional contract requirements for the system and has not been damaged<br />

during subsequent construction. This is normally a joint responsibility of C-P/DPW<br />

Chief Construction Engineer, Project Construction Manager, Field Inspector, Design<br />

Engineer, and Contractor and best held with all parties present at the same time.<br />

8.2 Quality Control<br />

The Contractor has the ultimate responsibility for the quality of the work and ensuring it<br />

meets all design and specification requirements. In addition, C-P/DPW will provide quality<br />

assurance inspection to confirm Contractor is achieving the project’s quality goals.<br />

The Contractor is required to meet with the Field Inspector prior to the start of a new phase<br />

of work in order to determine when quality control inspections will be required. For<br />

example, if the contractor is installing concrete footings, inspection will be required at the<br />

following times:<br />

<br />

<br />

<br />

At completion of excavation to ensure that the excavation conforms to the lines and<br />

grades of the work and that the bottom of the excavation has been compacted in<br />

accordance with the specification.<br />

At completion of the installation of forms and reinforcing steel to ensure that the forms<br />

conform to the lines and grades of the plans; that the steel has been installed according<br />

to approved shop drawings; and that all embeds are in place.<br />

During placement of concrete to ensure the quality of concrete meets the standards of<br />

the specification and that its placement is done in a manner that achieves the intent of<br />

the contract.<br />

GNV310133632155.DOC/090840001 8-1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!