R/3 does planning without consideration for capacity situations. So if MRP says you need<br />
500 parts on 3/1/04, it schedules them all to be built at the same time, even though you<br />
can only do 100 at a time. Assume you have a fixed lot size of 100, you'll get 5 planned<br />
orders for 100 to start on the same day. This is "Infinite <strong>Planning</strong>". APO would recognize<br />
that constraint, and instead schedule out the 5 orders over time. The important part of that<br />
is that it also will schedule out the deliveries of the components for 5 different days. This<br />
is "Finite <strong>Planning</strong>".<br />
Now, assume old fashion MRP. It schedules all 5 orders for the same day, and the buyers<br />
go out an get all of the components for the same day. Then the planner realizes he can't do<br />
all 5, and manually changes the schedule, and manually spreads out the 5 orders. The<br />
buyers will recieve rescheduling notifications, but not until the scheduler does the manual<br />
rescheduling. You could call this "Infinite Scheduling", but that only means the same<br />
thing as Infinite <strong>Planning</strong>.<br />
But, <strong>SAP</strong> has "Capacity Leveling". What that means is you run another program after<br />
MRP (CM27 and CM28), which can be run in batch mode overnight. (There is a ton of<br />
configuration and thinking that will be required to do this!). The capacity leveling<br />
program will recognize the constrant at the work center level, and fill up the first day,<br />
then re-schedule the next order to the next available capacity, then the next order searches<br />
for available capacity, and so on. This is called "Finite Scheduling". The problem with<br />
this is the opposite of Infinite <strong>Planning</strong>, which is it doesn't take Material availablity into<br />
consideration! The system will re-schedule a production order without thinking about<br />
whether the materials will be available or not.<br />
Finite <strong>Planning</strong> does Finite Sheduling at the same time. If there is no capacity available<br />
on the desired date, the system looks for when capacity IS available. Then it stops to see<br />
if Materials will also be available (usually based on the lead-time for those components).<br />
If there is a material problem, then the system figures out when the materials WILL be<br />
available, and then<br />
checks to see if capacity is available on THAT day, and if so, it blocks off capacity, and<br />
allocates the materials for that day.<br />
Do you have a <strong>SAP</strong> PP Question?<br />
Difference between MRP vs MPS<br />
Explain the difference between MRP & MPS. Though both components gives you<br />
the requirement list, what we gain out of MPS run rather than running MRP. What<br />
is the main idea behind this?<br />
The following might help in explaining the difference between MPS and its counter part<br />
MRP.<br />
Master <strong>Production</strong> Schedule (MPS) :<br />
MPS operates within only one level of the BOM, While MRP can be utilized throughout