production parameter in SchedMargin key?<br />

I know the parameter affection in production,but I am not sure why to define how<br />

many days in each parameter.<br />

for example, release key defined for 10 workdays,but you can release production<br />

order out of the release period randomly.any way to stop release out of the release<br />

period?<br />

For example - Component A has a lead time of 14 days and opening period of 5 days.<br />

Requirement on 12-22-03<br />

Opening Date - 12-01-03 ???<br />

Start Date - 12-08-03 (from requirement date - lead time ?)<br />

Finish Date - 12-22-03 (from requirement date ?)<br />

Why Openning date = 12/01/2003 how system calculate , Could you please explain to<br />

me..<br />

I know that when we run MRP system will check if the opening date is out of open<br />

period system will generate Plan order instead of PR .<br />

The times in the sch. margin key are in workdays. That's how it gets the dates. The<br />

component I was describing originally would have been a purchased part, where lead<br />

time is in calendar days.<br />

The order start date and the order finish date form the framework within which a<br />

production order is to be executed. Since malfunctions and disturbances in the production<br />

process can never be fully prevented, the system uses particular floats in a production<br />

order. The system takes into account so-called "before and after production floats" when<br />

scheduling an order.<br />

The float before production is a start float. It has two functions:<br />

It can compensate for delays in the staging of the material components.<br />

If there is a capacity bottleneck at the work centers involved, the production dates can be<br />

moved forward in the future. In this way it serves as a float for capacity leveling.<br />

The float after production is a finish float. It is used to compensate for unexpected<br />

disturbances in the production process, so that they do not delay the scheduled finish<br />

date.<br />

The floats before and after production are defined for each material using a scheduling<br />

margin key. This scheduling margin key is automatically transferred from the material<br />

master when an order is created. However, you can change the times in the order.<br />

The system calculates the scheduled start of the order by adding the float before<br />

production to the order start date. It calculates the scheduled finish of the order by<br />

subtracting the float after production from the order finish date.